HomeMy WebLinkAboutPowerPoint -DubCHurch.pptDubuque Street Church Street
&
Intersection Improvements Project
Project Location Map
Dubuque Street and Church Street Intersection
Improvements Project
Operational Issues
•Bus movements at the intersection
?High priority with the University
?Creates gridlocked conditions
•Current capacity Issues
?Tight geometry
?Re-timing current signal does not increase capacity
Dubuque Street and Church Street Intersection Improvements
Project
Project Overview
•Install Wider Radius at Northwest Quadrant of Intersection
•Widen Dubuque Street
?300‘North and South of Church Street Intersection
?Allows for left turn lane N-S
•Widen Church Street
?200‘East and West of Dubuque Street Intersection
?Added Curb section to street allows for left turn lane E-W
•Install New Traffic Signal System at Intersection
•Install New Sidewalks and ADA Compliant Curb Ramps at Intersection
•30 year Improvement
Iowa River Landing Entrance
Existing Church Street
•Curb Section Adjacent to
•Curb Section in Poor Condition
Brick Pavers
•Brick in Marginal Condition
Progress to Date
•Topographic Survey -70%
•Utility Survey -50%
•Right of Way Surveys –90%
•Iowa DOT Concept Plan Submittal –Completed November 2006
Next Step
•Authorization By Council to proceed with Iowa DOT Agreement
?$400,000 allocated in STP Funds through JCCOG
Project Schedule
June 12, 2007
•Complete Acquisition and Easement Plats
•Complete Preliminary Design and Plan of Improvements
August 21, 2007
•Complete Check Plans
December 18, 2007
•Final Plans and Project Development
•Allows for 6 Month Condemnation Term
March 18, 2008
•Project Letting
Summer 2008
•Complete Construction