Fire Station #2
RAPC Project No. 0623
Iowa City Fire Department
City of Iowa City
Summary Statement of Probable Construction Costs/Areas
April 16, 2007
Study Phase Schematic Design Phase
Item Cost ItemAreaCostsArea Costs
No.SF$/SF$SF$/SF$
1Original Size and Cost of Firestation7,064$1,300,0007,064$1,300,000
Program Items added to the Project
2 Basement to Accommodate Future GrowthNA2,290$229,000
3 Extention of Services (i.e. emergency medical services)NA1,359$277,000
4 Upfront cost for Increased Long-term Energy Efficiency NA$136,000
Additional Items not in Original Program
NA$40,000
5 Water Main Relocation
6Total Construction Costs7,064$184$1,300,00010,300$192$1,980,000