HomeMy WebLinkAbout2007-04-16FireStation#2.pptOption D Site Plan Existing Site Plan Outline of Existing Building New Building Site Plan New Building Site Plan Main Level Floor Plan Lower Level Floor Plan East Elevation North Elevation West Elevation South Elevation Fire Station #2 RAPC Project No. 0623 Iowa City Fire Department City of Iowa City Summary Statement of Probable Construction Costs/Areas April 16, 2007 Study Phase Schematic Design Phase Item Cost ItemAreaCostsArea Costs No.SF$/SF$SF$/SF$ 1Original Size and Cost of Firestation7,064$1,300,0007,064$1,300,000 Program Items added to the Project 2 Basement to Accommodate Future GrowthNA2,290$229,000 3 Extention of Services (i.e. emergency medical services)NA1,359$277,000 4 Upfront cost for Increased Long-term Energy Efficiency NA$136,000 Additional Items not in Original Program NA$40,000 5 Water Main Relocation 6Total Construction Costs7,064$184$1,300,00010,300$192$1,980,000