HomeMy WebLinkAbout4/4/14 energyreview
Generated by RES check-Web Software
Compliance Certificate
2009 IECC
Energy Code:
Iowa City, Iowa
Location:
Single Family
Construction Type:
Bldg. faces 0 deg. from North
Building Orientation:
3282 ft2
Conditioned Floor Area:
14%
Glazing Area Percentage:
6227
Heating Degree Days:
5
Climate Zone:
Construction Site:Owner/Agent:Designer/Contractor:
Two-StorySouthgate HomesJim Walker
Iowa City, IowaIowa City, IowaSoutgate Homes
Passes using performance alternative
Compliance:
5.3% Better Than Code
Compliance:
GrossCavityCont.GlazingUA
AssemblyArea orR-ValueR-Valueor Door
PerimeterU-Factor
Ceiling: Raised or Energy Truss127649.03.024
Front- Main and Upper Wall: Wood Frame, 16in. o.c.108019.02.051
Orientation: Front
Door: Solid500.27014
Orientation: Front
Window: Vinyl Frame, 2 Pane w/ Low-E730.29021
SHGC: 0.22
Orientation: Front
Left - Main and Upper Wall: Wood Frame, 16in. o.c.40119.02.017
Orientation: Left Side
Window: Vinyl Frame, 2 Pane w/ Low-E770.29022
SHGC: 0.22
Orientation: Left Side
Right - Main and Upper Wall: Wood Frame, 16in. o.c.40019.02.021
Orientation: Right Side
Window: Vinyl Frame, 2 Pane w/ Low-E70.2902
SHGC: 0.22
Orientation: Right Side
Rear - Main, Upper and Lower Wall: Wood Frame, 16in. o.c.123519.02.051
Orientation: Back
Door: Glass840.29024
SHGC: 0.23
Orientation: Back
Window: Vinyl Frame, 2 Pane w/ Low-E1800.29052
SHGC: 0.22
Orientation: Back
Floor abv Garage: All-Wood Joist/Truss Over Uncond. Space14430.02.04
Front -Basement: Solid Concrete or Masonry74113.02.036
Orientation: Front
Wall height: 9.0'
Depth below grade: 8.5'
Insulation depth: 9.0'
Left - Basement: Solid Concrete or Masonry21313.02.011
Orientation: Left Side
Wall height: 9.0'
Depth below grade: 8.0'
Insulation depth: 9.0'
Right - Basement: Solid Concrete or Masonry18013.02.09
Project Title: Report date: 09/22/11
Data filename: Page 1 of 6
Orientation: Right Side
Wall height: 9.0'
Depth below grade: 8.5'
Insulation depth: 9.0'
Furnace: Forced Hot Air 92 AFUE
Air Conditioner: Electric Central Air 14.5 SEER
Compliance Statement: The proposed building design described here is consistent with
calculations submitted with the permit application. The proposed
RES check-Web and to comply with the mandatory requirements listed in the RES check Inspection Checklist.
Name - TitleSignatureDate
Project Title: Report date: 09/22/11
Data filename: Page 2 of 6
Generated by RES check-Web Software
Inspection Checklist
Ceilings:
q
Ceiling: Raised or Energy Truss, R-49.0 cavity + R-3.0 continuou
Comments:
Insulation must achieve full height over the plate lines of exte
Above-Grade Walls:
q
Front- Main and Upper Wall: Wood Frame, 16in. o.c., R-19.0 cavit
Continuous insulation specified for this above-grade wall has co
Comments:
q
Left - Main and Upper Wall: Wood Frame, 16in. o.c., R-19.0 cavit
Continuous insulation specified for this above-grade wall has co
Comments:
q
Right - Main and Upper Wall: Wood Frame, 16in. o.c., R-19.0 cavi
Continuous insulation specified for this above-grade wall has co
Comments:
q
Rear - Main, Upper and Lower Wall: Wood Frame, 16in. o.c., R-19.
Continuous insulation specified for this above-grade wall has co
Comments:
Basement Walls:
q
Front -Basement: Solid Concrete or Masonry, 9.0' ht / 8.5' bg /
Comments:
q
Left - Basement: Solid Concrete or Masonry, 9.0' ht / 8.0' bg /
Comments:
q
Right - Basement: Solid Concrete or Masonry, 9.0' ht / 8.5' bg /
Comments:
Windows:
q
Window: Vinyl Frame, 2 Pane w/ Low-E, U-factor: 0.290
For windows without labeled U-factors, describe features:
#Panes Frame Type Thermal Break? Yes No
Comments:
q
Window: Vinyl Frame, 2 Pane w/ Low-E, U-factor: 0.290
For windows without labeled U-factors, describe features:
#Panes Frame Type Thermal Break? Yes No
Comments:
q
Window: Vinyl Frame, 2 Pane w/ Low-E, U-factor: 0.290
For windows without labeled U-factors, describe features:
#Panes Frame Type Thermal Break? Yes No
Comments:
q
Window: Vinyl Frame, 2 Pane w/ Low-E, U-factor: 0.290
For windows without labeled U-factors, describe features:
#Panes Frame Type Thermal Break? Yes No
Comments:
Doors:
Project Title: Report date: 09/22/11
Data filename: Page 3 of 6
q
Door: Solid, U-factor: 0.270
Comments:
q
Door: Glass, U-factor: 0.290
Comments:
Floors:
q
Floor abv Garage: All-Wood Joist/Truss Over Uncond. Space, R-30.
Comments:
Floor insulation is installed in permanent contact with the unde
Heating and Cooling Equipment:
q
Furnace: Forced Hot Air: 92 AFUE or higher
Make and Model Number:
q
Air Conditioner: Electric Central Air: 14.5 SEER or higher
Make and Model Number:
Air Leakage:
Joints (including rim joist junctions), attic access openings, p
q
sources of air leakage are sealed with caulk, gasketed, weathers
solid material.
Air barrier and sealing exists on common walls between dwelling
q
window/door jambs and framing.
Recessed lights in the building thermal envelope are 1) type IC
q
between the housing and the interior wall or ceiling covering.
Wood-burning fireplaces have gasketed doors and outdoor combusti
q
Air Sealing and Insulation:
Building envelope air tightness and insulation installation comp
q
ACH at 33.5 psf OR 2) the following items have been satisfied:
(a)
Air barriers and thermal barrier: Installed on outside of air-pe
repaired.
(b)
Ceiling/attic: Air barrier in any dropped ceiling/soffit is subs
(c)
Above-grade walls: Insulation is installed in substantial contac
(d)
Floors: Air barrier is installed at any exposed edge of insulati
(e)
Plumbing and wiring: Insulation is placed between outside and pi
sprayed/blown insulation extends behind piping and wiring.
(f)
Corners, headers, narrow framing cavities, and rim joists are in
(g)
Shower/tub on exterior wall: Insulation exists between showers/t
Materials Identification and Installation:
Materials and equipment are installed in accordance with the man
q
Insulation is installed in substantial contact with the surface
q
Materials and equipment are identified so that compliance can be
q
Manufacturer manuals for all installed heating and cooling equip
q
Insulation R-values, glazing U-factors, and heating and cooling
q
specifications.
Duct Insulation:
All ducts not completely inside the building envelope are insula
q
Duct Construction and Testing:
Building framing cavities are not used as supply ducts.
q
All joints and seams of air ducts, air handlers, filter boxes, a
q
of tapes, mastics, liquid sealants, gasketing or other approved
UL 181B and are labeled according to the duct construction. Meta
fastened. Crimp joints for round metal ducts have a contact lap
equally spaced sheet-metal screws.
Exceptions:
Joint and seams covered with spray polyurethane foam.
Project Title: Report date: 09/22/11
Data filename: Page 4 of 6
Where a partially inaccessible duct connection exists, mechanica
joint so as to prevent a hinge effect.
Continuously welded and locking-type longitudinal joints and sea
Duct tightness test has been performed and meets one of the foll
q
(1)
Postconstruction leakage to outdoors test: Less than or equal to
(2)
Postconstruction total leakage test (including air handler enclo
conditioned floor area) pressure differential of 0.1 inches w.g.
(3)
Rough-in total leakage test with air handler installed: Less tha
when tested at a pressure differential of 0.1 inches w.g.
(4)
Rough-in total leakage test without air handler installed: Less
Temperature Controls:
At least one programmable thermostat is installed to control the
q
the heating cycle and 78 degree F for the cooling cycle.
Heating and Cooling Equipment Sizing:
Additional requirements for equipment sizing are included by an
q
For systems serving multiple dwelling units documentation has be
q
Building Mechanical and/or Service Water Heating (Sections 503 a
Circulating Service Hot Water Systems:
Circulating service hot water pipes are insulated to R-2.
q
Circulating service hot water systems include an automatic or ac
q
system is not in use.
Heating and Cooling Piping Insulation:
HVAC piping conveying fluids above 105 degrees F or chilled flui
q
Swimming Pools:
Heated swimming pools have an on/off heater switch.
q
Pool heaters operating on natural gas or LPG have an electronic
q
Timer switches on pool heaters and pumps are present.
q
Exceptions:
Where public health standards require continuous pump operation.
Where pumps operate within solar- and/or waste-heat-recovery sys
Heated swimming pools have a cover on or at the water surface. F
q
minimum insulation value of R-12.
Exceptions:
Covers are not required when 60% of the heating energy is from s
Other Requirements:
Snow- and ice-melting systems with energy supplied from the serv
q
off the system when a) the pavement temperature is above 50 degr
above 40 degrees F (a manual shutoff control is also permitted t
Certificate:
A permanent certificate is provided on or in the electrical dist
q
U-factors; type and efficiency of space-conditioning and water h
of the circuit directory label, service disconnect label or othe
NOTES TO FIELD:
(Building Department Use Only)
Project Title: Report date: 09/22/11
Data filename: Page 5 of 6
Project Title: Report date: 09/22/11
Data filename: Page 6 of 6
2009 IECC Energy
Efficiency Certificate
Insulation RatingR-Value
Ceiling / Roof52.00
Wall21.00
Floor / Foundation15.00
Ductwork (unconditioned spaces):_____
Glass & Door RatingU-FactorSHGC
Window0.290.22
Door0.290.23
Heating & Cooling EquipmentEfficiency
Forced Hot Air Furnace92 AFUE
Electric Central Air Conditioner14.5 SEER
Water Heater:___________________________
Name:Date:
Comments: