HomeMy WebLinkAbout05-21-2009 Airport CommissionIOWA CITY AIRPORT COMMISSION
MEETING AGENDA
AIRPORT TERMINAL BUILDING
1801 S. RIVERSIDE DRIVE
IOWA CITY, IOWA
THURSDAY, MAY 21, 2009 - 6:OOP.M.
1. Determine Quorum
2. Approval of Minutes from the following meetings:
April 16, 2009; May 6, 2009
3. Public Discussion - Items not on the agenda
4. Items for Discussion/Action:
a. Aviation Commerce Park / Uofl Aircare Facility
b. Gilbert Street Land Parcel
i. Public Hearing — Lease with Larry Bell
ii. Consider a resolution approving lease with Larry Bell
c. Private Hangar Construction — Doug Moore
d. Farmer's National / Merschman Seeds
i. Consider a resolution setting public hearing for lease amendment
e. FAA/IDOT Projects - AECOM — David Hughes
i. Runway 7/25 & 12/30
1. Consider a resolution authorizing chair to accept FAA grant 4v9-//
awards
2. Consider a resolution accepting bids and awarding project ,,z i - /d
3. Consider a resolution approving task order #3 with AECOM tje9-/3
4. Consider a resolution approving task order #4 with AECOM
ii. South Aviation Development Study
1. Consider a resolution accepting South Airfield Planning Study
iii. 2008 Pavement Rehab (North Taxilanes)
iv. Obstruction Mitigation
v. Building H — University of Iowa Hangar Expansion
f. Hangar #56 — Sublease Request
g. Airport "Operations": Strategic Plan -Implementation; Budget; Management
h. FBO Staff Report
i. Subcommittees' Reports
j. Commission Members' Reports
k. Staff Report
5. Set next regular meeting for June 18, 2009 at 6:00 p.m.
6. Adjourn
MINUTES DRAFT
Iowa City Airport Commission
April 16, 2009
Iowa City Airport Terminal — 6:00 PM
Members Present: Greg Farris, Minnetta Gardinier, Howard Horan, Janelle Rettig,
John Staley
Staff Present: Sue Dulek, Michael Tharp, Sarah Holecek
Others Present: David Hughes, Jay Honeck, Rex Brandstatter, Doug Moore, Larry
Bell, John Yeomans, Peggy Slaughter
RECOMMENDATIONS TO COUNCIL: None
DETERMINE QUORUM:
Chairperson Rettig called the meeting to order at 6:00 P.M. Rettig noted that Sarah
Holecek is present at tonight's meeting, from the City Attorney's office, filling in for Sue
Dulek.
APPROVAL OF MINUTES FROM THE MARCH 12, APRIL 2, AND APRI L 14,
2009 MEETINGS:
Rettig asked if anyone had any changes to the March 12 minutes. Staley moved to
approve the minutes of the March 12, 2009 meeting as submitted; seconded by
Farris. Carried 4-0 (Gardinier absent).
Rettig asked if anyone had any changes to the April 2 minutes. Farris moved to
approve the minutes of the April 2, 2009 meeting as submitted; seconded by Horan.
Carried 5-0.
Rettig then asked if anyone had any changes to the April 14 minutes. Farris moved to
approve the minutes of the April 14, 2009 meeting as submitted; seconded by Rettig.
Carried 5-0.
PUBLIC DISCUSSION:
None.
ITEMS FOR DISCUSSION/ACTION:
a. Aviation Commerce Park / U of I Aircare Facility - (Staley recused himself as
an Airport Commission Member and participated in this discussion as a UIHC
employee.)
Iowa City Airport Commission
April 16, 2009
Page 2 of 8
Staley noted that they met on March 26 and are moving ahead. They first
need to obtain two independent appraisals, and have commissioned two firms
to do these appraisals. They hope to have this done in the next week or so.
Peggy Slaughter noted that one of the firms contacted her today. Slaughter
noted some other opportunities, one being a group from Waterloo who is
interested in the Aviation Commerce Park lots. She continued, giving the
Members a quick update on some of the other interested parties. Slaughter
asked if anyone knows the timeframe for the new Wal-Mart store. Tharp
noted that the Staples store has to be completed first, and that its due to be
open in August or September. Slaughter also noted that they have the listings
for the Aviation Commerce Park on www.loopnet.com - a service that "loops"
you back to their web site.
b. Gilbert Street Land Parcel - Tharp noted that representatives are not present
this evening, and that he has not heard anything further from them. Staley
moved that they defer this item until the parry's arrival; seconded by
Farris. Carried 5-0.
c. Private Hangar Construction - Doug Moore - Tharp noted that he spoke to
Doug Moore recently. Moore is still gathering information for his proposal.
Horan stated that he wanted to make a comment for the record - he believes
they need to make it very clear that any sort of reclamation or salvage
operation will not be left outside. He believes this is important in considering
Moore's proposal. Tharp noted that he has received the same comment from
others. Farris asked what zoning considerations would come into play in a
situation like this. Tharp noted that the Airport has its own Zoning Board.
Holecek responded to the Members' discussion, noting how overlay zoning
would come into play here. Horan stated that he would make the motion, if
need be, that they do not allow the Airport to become a "junkyard," that there
should be no evidence outside of the hangar that there is a salvage operation
there. Rettig noted that instead of a formal motion this should be a consensus
of the Airport Commission that they are directing Tharp to continue the
negotiations with Mr. Moore, keeping in mind that should this come to
fruition, there will be nothing outside of the hangar in the form of a salvage
operation.
d. Farmer's National / Merschman Seeds - John Yeomans spoke to the
Commission concerning Merschman Seeds. He stated that they are interested
in extending their lease with the Airport. Rettig noted that the current lease
expires in February of 2010. He added that Merschman Seeds would like to
do some beautification of the area, and in return for taking care of this project,
they would like to be able to count on being at the Airport for the next few
years. The discussion turned to the impact of the runway closures this season,
and Yeomans noted that Merschman is aware of this. Rettig asked Yeomans
how the agricultural seed business is doing, and he gave a brief rundown of
2
Iowa City Airport Commission
April 16, 2009
Page 3 of 8
tightening margins and struggles with prices. He added that the ethanol
business has basically imploded, and that things have changed dramatically
over the past year. The discussion turned to lease rates, and Yeomans noted
that most are staying at the same rates. Members discussed this briefly with
him. Horan noted that a two-year lease would most likely not interfere with
any of the Airport's plans, and others agreed with him. Tharp noted that the
next thing that would interfere with this area is the perimeter road project, and
that is slated for October of 2012. Members then discussed the amount of the
current contract - $25,000 - with Tharp explaining how Farmer's National gets
a small portion of this for management of Merschman Seeds. Farris stated
that he sees no problem in a two-year lease, and Rettig agreed, adding that
they need to make sure that the problems seen last year - a gate left open and
banners that were left hanging - are addressed ahead of time so that this does
not occur again. Members agreed that Dulek would need to review this lease,
and that they are interested in pursuing another two years. The discussion
moved back to the beautification project that Merschman Seeds is proposing,
with Yeomans clarifying what is intended. Holecek noted that they could
enter into a Temporary Use of Right -of -Way agreement, which would allow
Merschman to use the right-of-way, but contains an indemnification provision
in case anything would happen. The topic moved back to what the Airport is
charging in this land lease with Merschman Seeds. Yeomans responded to
Members' questions regarding the current market price for this type of
contract. There was a consensus among the Members to move forward with
another two-year lease with Farmer's National and Merschman Seeds.
e. FAA/IDOT Projects —AECOM — David Hughes
i. Runways 7/25 & 12/30 - Hughes stated that they have been quite
busy since the last meeting. There is a pre -bid conference next
Tuesday afternoon at 1:30. The bids are due the 29th of this
month, and Hughes stated that they plan to have the grant
application back to the FAA the following day then. Hughes
continued, stating that the phasing plans are set up per some of the
previous discussions regarding this. He added that the Airport
would not be closed between July 24th and August 3rd, and also
August 29th and 30th. The intersection closure has been set for a
28-day calendar period, according to Hughes, and hopefully the
weather will cooperate. Gardiner asked for some clarification on
the various phases, and Hughes responded. Hughes noted that he
should have a better idea of closure dates once they have the pre -
construction conference. It was noted too, for clarification, that the
Airport itself will not be closed - the runways will be closed -
during the upcoming construction period.
1. Consider Resolution #A09-06 Accepting Work for Runway
7-25 Extension (Phase 5) Paving and Lighting - Hughes
noted that the project ended up about $7,000 under the initial
Iowa City Airport Commission
April 16, 2009
Page 4 of 8
construction cost. Farris moved Resolution #A09-07;
seconded by Horan. Carried 5-0.
ii. South Aviation Development Study — Hughes noted that they did
receive comments back from the FAA. The good news is that the
FAA is going to treat the South Aviation Development Study as a
stand-alone document, which means they do not have to wait for
approval on the Airport Layout Plan documents. The bad news,
according to Hughes, is that he has been so busy that he has not
been able to return this document to the FAA yet. He hopes to get
this out early next week. Tharp noted that once the approved
documents are returned, they would need to set up a joint meeting
with the City Council to present this.
iii. 2008 Pavement Rehab (North Taxilanes) — Hughes stated that they
have not talked to Pelling yet, but plan to call in the next few
weeks to get them back for the needed repairs.
iv. Obstruction Mitigation — Hughes asked Tharp if he had received a
bill from Mediacom on this. Tharp stated that he had not. Hughes
added that they are still trying to complete the United hangar
demolition paperwork, as well. Rettig noted that the land around
the fence area looks like it is settling, and Hughes stated that he
would look at this area to see what is happening.
V. Building H — University of Iowa Hangar Expansion — Tharp noted
that they ran into some preliminary problems regarding the
location of underground utilities, and he briefly filled Members in
on this.
vi. FY2010 State Aviation Program Grant Application - Hughes
explained the four projects that make up this application - the
drainage for Hangar A, overlay taxiway leading to runway 2-5,
south area pavement maintenance, and pavement maintenance in
front of the main terminal building and along the taxiway. Hughes
added that they will have to see what the State is willing to fund -
it could be just two, it could be all four. Hughes continued to
respond to Members' questions as they reviewed the upcoming
years' projects. Farris moved to approve the FY2010 State
Aviation Grant application; seconded by Staley. Carried 5-0.
b. Larry Bell, owner of the property, and Rex Brandstatter joined the Airport
Commission meeting at this time. Brandstatter addressed the Members,
stating that he hoped everyone had had a chance to review his letter. He noted
that the details not addressed in the letter include the length of a lease and any
specifics that City code would dictate. Horan asked what type of term they
are interested in, and Brandstatter responded that probably something in the
20 to 25 year range, being renewable upon review. Tharp stated that he did
some of his own research, and found that $300 a month is a very fair rate. As
for the length of the lease, Tharp recommended doing five-year increments,
4
Iowa City Airport Commission
April 16, 2009
Page 5 of 8
on a 20-year lease, with a CPI inflator every five years. Tharp added that the
best use for this piece of property would be something like this proposal.
Horan added that he believes they should make it a "floor of $300" in case the
CPI inflator would not go up. Dulek added that they will need to have a
public hearing, first of all, and that she and Tharp can work on a lease
agreement for the Commission to review. Bell added that his concern is
putting $25,000 to $40,000 into something like this and then not having it be
feasible after a five-year period. Members continued to discuss this proposal,
with unanimous agreement that Dulek and Tharp will begin working on a
lease proposal. This led the Commission to discuss when they would need to
hold the public hearing. Rettig suggested May 12th at 7:30 A.M., and others
agreed.
f. Airport "Operations;" Strategic Plan -Implementation; Budget; Management —
Tharp began the discussion, stating that the big issue is the City's budget
shortfall. This has led to all departments being asked to cut their budgets for
fiscal year 2010 and beyond. Tharp continued, stating that he has a memo
from the City Manager's office asking for various scenarios, such as 1, 2, and
4% reductions in General Fund budget appropriations. Tharp stated that he
believes they will be able to absorb any of the proposed cuts. He added that
he would like to have the authority to go ahead and work on this. Members
began to discuss this issue, with Tharp responding to questions on what his
proposals will be. Staley stated that he could be comfortable with Tharp
working on this with the Chair, and others agreed. Rettig then noted that on
page 7 there is a line charge for the position of the Economic Development
person. She added that she believes this charge should be brought up in light
of budget cuts. Farris noted that this has been brought up yearly and that
nothing has changed thus far. The discussion turned to some of the items that
need attention at the Airport. Tharp noted that the boiler needs to be repaired,
in addition to some other items. He stated that he would like to review the
capital funds of approximately $70,000 in order to cover these items. Another
item is an asphalt overlay of the area at the front of the terminal, which Tharp
expects to use a big chunk of these funds. Repairing the back door at the
terminal and purchasing paint are the other items that Tharp would like to
cover with these fiords. Staley moved to authorize Tharp, with approval of
the Chair, to use capital funds to cover the boiler repair, asphalt overlay,
door repair, and paint purchase, as discussed above; Horan seconded.
Carried 5-0. Rettig then asked if Tharp believes the transition to having Jet
Air do the maintenance is working. He responded that after some initial
bumps in the road things appear to be working out. The discussion continued,
with Members discussing the possible need of a checklist of sorts to make
sure the maintenance is kept up in crucial areas. As for the cleaning portion of
the contract, Tharp noted that this has improved. The discussion then turned
to the strategic plan. Staley noted that he met with Rettig and Tharp to lay out
a timeline to get this plan going. They are planning on it going into effect in
Iowa City Airport Commission
April 16, 2009
Page 6 of 8
July of 2010. Farris suggested they be proactive in the sense that they look at
how the Airport can trim the budget, as the City has asked, over a longer time
period. Rettig added that the meetings for the strategic planning would start
this fall. Rettig then noted that Jet Air's attorney contacted Dulek regarding
an FBO management agreement reduction of fees of 50% during the time that
the runways are closed. Faros then noted what the Airport pays Jet Air for
both cleaning and maintenance each month. This led to a brief discussion
among Members, with Rettig stating that she believes this closure is
unfortunate but that everyone involved will benefit from this project once it is
completed. The Commission Members agreed unanimously that they do not
feel the Airport should grant a fee reduction to Jet Air. Gardinier then spoke
as a member of the public regarding this issue, stating that it is a bit
disingenuous to view the hangars as solely storage space for airplanes without
having any expectation that individuals would need runway access. She
added that she did some looking around and found a State of Wisconsin
Department of Transportation document used for leases, and this document
does state that if runways are closed, the lessee will be given credit for the
time they are unable to utilize the runways.
g. Airport Commission Bylaws - Rettig noted that Members received a memo
from Dulek regarding changes to the Airport Commission's bylaws, one being
a change from 6-year terms to 4-year terms; the next is to change the "Vice
Chairperson" position to "Secretary"; and third would be to delete the
requirement that the Vice Chairperson must certify bills for approval. Staley
moved to approve the changes to the Airport Commission Bylaws as
discussed, seconded by Horan. Carried 5-0. Dulek noted that she will get
copies of the revised bylaws to Members once this is updated.
h. FBO Staff Report - Rettig noted that she had a message from Jet Air, noting
that due to a funeral and travel, no one would be available at tonight's
meeting.
i. Subcommittees' Reports — Rettig noted that they need another Member for the
Budget Subcommittee, now that Hartwig has left. Farris stated that he would
serve, and others agreed to this. Farris then spoke to Members about the
viewing area and the upcoming plans for this season. Rettig noted that they
need to put some concrete stops in so cars are not parked on the sidewalk area
here, as it makes the sidewalk hard to use. She also noted that the last parking
spot was where they were going to put the bike rack that has still not been
installed. She asked that these two items be part of the viewing area tasks,
and that they address them this year.
Commission Members' Reports — Horan brought up the issue of a grant
summary, and asked if Tharp could prepare such a document. He believes
this will be a valuable tool for the Airport. Rettig reminded everyone that
Iowa City Airport Commission
April 16, 2009
Page 7 of 8
Tharp is working on a newsletter and the next one is due out the first part of
May, in case anyone has something to add to this next issue. Gardinier asked
if the newsletter comes out regularly, and Tharp noted that it was supposed to
be quarterly, but that this does not always happen. Rettig noted that it would
be helpful to have a "communications intem" to help with some of these new
avenues, such as Twitter, Facebook, and the web page. Gardinier asked if
anyone had checked with the University on the possibility of graduate
students fulfilling such a need. Members agreed that this would be a good
idea and would be worth looking into.
k. Staff Report — Tharp reminded the Members that next week is the Aviation
Conference, Wednesday and Thursday. Gardinier stated that she will be there
on Wednesday.
SET NEXT REGULAR MEETING: Thursday, May 21, 2009 at 6:00 P.M. A special
meeting will be held May 12, 2009 at 7:30 A.M.
ADJOURN: The meeting adjourned at 8:31 P.M. Moved by Horan to adjourn,
seconded by Farris. Carried 5-0.
7
Iowa City Airport Commission
April 16, 2009
Page 8 of 8
Airport Commission
ATTENDANCE RECORD
YEAR 2009
Betio Dates
NAME
TERM
EXP.
1/8
2/5
2/12
3/12
4/2
4114
4116
5/12
5/21
Greg Farris
3/1113
X
X
X
X
X
X
X
Minnetta
Gardinier
3/1/15
—
—
—
X
X
X
X
Howard Horan
311/14
X
X
X
X
O/E
O/E
X
JanelleRettig
3/1/12
X
O/E
X
X
X
X
X
John Staley
3/1/10
X
O/E
X
X
O/E
O/E
X
KEY: X = Present
O = Absent
O/E = Absent/Excused
NM = No meeting
-- = Not a Member
MINUTES
Iowa City Airport Commission
May 6, 2009
Iowa City Airport Terminal — 7:30 AM
Members Present: Greg Farris, Howard Horan, John Staley, Janelle Rettig
Staff Present: Sue Dulek
Others Present: None
RECOMMENDATIONS TO COUNCIL:
None
DETERMINE QUORUM:
The meeting was called to order at 7:31 AAL
ITEMS FOR DISCUSSION/ACTION:
DRAFT
1. Consider a resolution setting a public hearing for a ground lease with Larry E. Bell and
Sandra S. Bell. Horan moved to consider Resolution No. A09-08 setting a public hearing
for a ground lease with Larry E. Bell and Sandra S. Bell. Farris seconded. Resolution
carried 4-0.
ADJOURN: Farris moved to adjourn, Horan seconded. Motion carried 4-0. The
meeting adjourned at 7: 32 A.M.
Iowa City Airport Commission
April 16, 2009
Page 2 of 2
Airport Commission
ATTENDANCE RECORD
YEAR 2009
(Meeting Dates)
NAME
TERM
EXP.
1/8
215
2/12
3/12
4/2
4/14
4/16
5/6
5/21
Greg Farris
3/1/13
X
X
X
X
X
X
X
X
Minnetta
Gardinier
3/1/15
—
—
—
X
X
X
X
O/E
Howard Horan
3/1/14
X
X
X
X
WE
O/E
X
X
Janelle Rettig
3/1/12
X
O/E
X
X
X
X
X
X
John Staley
3/1/10
X
O/E
X
X
O/E
O/E
X
X
KEY: X = Present
O = Absent
O/E = Absent/Excused
NM = No meeting
— = Not a Member
Prepared by: Susan Dulek, Assistant City Attorney, 410 E. Washington St., Iowa City, IA 52240 (319) 356-5030
RESOLUTION NO.
RESOLUTION AUTHORIZING THE CHAIRPERSON TO SIGN AND THE
SECRETARY TO ATTEST TO A GROUND LEASE LARRY E. BELL AND
SANDRA S. BELL.
WHEREAS, Larry E. Bell and Sandra S. Bell would like to enter into a lease to park vehicles on
airport property north of 1565 S. Gilbert Drive; and
WHEREAS, public hearing was held on the proposed lease on May 21, 2009; and
WHEREAS, the lease of said space is in the public interest.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF IOWA
CITY, IOWA, THAT:
The Chairperson is hereby authorized to sign and the Secretary to attest to the Ground Lease,
a copy of which is attached and incorporated herein.
Passed and approved this day of
ATTEST:
SECRETARY
It was moved by
adopted, and upon roll call there were:
AYES:
9
CHAIRPERSON
and seconded by
NAYS:
Appr ved by
City Attorney's Office
ABSENT:
Farris
Gardinier
Horan
Rettig
Staley
the Resolution be
Prepared by: Susan Dulek, Ass't. City Attorney, 410 E. Washington St.; Iowa City, IA 52240; 319-356-5030
GROUND LEASE
THIS LEASE agreement made and entered into by and between Larry E. Bell and Sandra S. Bell
("TENANT"), and the Iowa City Airport Commission ("COMMISSION') in Iowa City, Iowa.
In consideration of their mutual promises herein, COMMISSION and TENANT agree as follows:
I. Leased Area. COMMISSION does hereby lease to TENANT the approximate 10,000
square foot area of vacant land depicted on Exhibit A and legally described in Exhibit B, which are
attached and incorporated herein, and located within the runway protection zone legally described
in Paragraph 3 below ("Leased Area").
2. Term. The term of this Lease will be from the date of execution to May 31, 2029.
TENANT shall have the option of an additional ten (10) year term, if written notification is given
to the COMMISSION by May 1, 2029— Rent for the additional ten-year term if the option is
requested shall be based on the "Rent Adjustment" provision described in Paragraph 3 below.
In the event TENANT shall continue to occupy the Leased Area beyond the term of this Lease
Agreement without executing an agreement for another term, such holding over shall not
constitute a renewal of this Lease Agreement but shall be on a month -to -month basis only.
3. Rent. TENANT shall pay $300.00 per month in rent, payable in advance on the first day of
each month. A 1.5% late fee ($4.50 per day) for rent not received by the COMMISSION will be
charged after the fifteenth (151h) day of each month. Rent for May 2009 shall be $96.00 which is
prorated from May 22 to May 31, 2009 and is due June 1, 2009.
Rent Adjustments. A consumer price index ("CPI") evaluation shall occur prior to and take effect
on May 1, 2014 and thereafter every five years of this Lease and additional exercised options. Said
rent adjustment shall reflect the change in the CPI for the previous five (5) year period, unless a
downward adjustment would occur. The CPI used shall be the data for the CPI-U, US City
Average, All Items Less Food and Energy, Base Period 1982-1984=100.
4. Permitted Use. TENANT shall use the Leased Area for vehicle parking, but only to the
extent permitted by FAA regulations, directives, rules, and policies and City of Iowa City
ordinances. TENANT shall be responsible for all improvements and future maintenance of the
Leased Area. TENANT intends to install either a concrete or asphalt parking lot in the Leased
Area.
2
5. RPZ. TENANT specifically acknowledges that the Leased Area is within the runway
protection zone ("RPZ") of the Iowa City Municipal Airport and that, as a result, the FAA restricts
certain uses within Leased Area. TENANT further acknowledges and agrees that the rights
granted to TENANT in this Lease will not be exercised so as to interfere with or adversely affect
the use, operation, maintenance or development of the Airport. This Lease shall be subordinate to
the provisions of any outstanding or future agreement between the Iowa City Airport Commission
and the United States government or the COMMISSION and the State of Iowa relative to the
maintenance, operation, or development of the Iowa City Municipal Airport.
6. Indemnification. TENANT agrees to indemnify, .defend and hold harmless the
COMMISSION and the City of Iowa City, their officers, agents and employees from and against
any and all claims, losses, liabilities or damages, of whatever nature, including payment of
reasonable attorney fees, arising from occurrences or accidents within the Leased Area, from the
TENANT'S use arising from this Lease agreement, or which may be caused in whole or in part
by any act or omission of the TENANT including their agents or employees.
7. Subleasing. TENANT shall not sublease the Leased Area or assign this Lease without the
prior written approval of the Commission, which approval shall not be unreasonably withheld.
S. Anti -Discrimination. TENANT shall not discriminate against any person in employment
or public accommodation because of race, religion, color, creed, gender identity, sex, national
origin, sexual orientation, mental or physical disability, marital status or age. "Employment" shall
include but not be limited to hiring accepting, registering, classifying, promoting, or referring to
employment. "Public accommodation" shall include but not be limited to providing goods,
services, facilities, privileges and advantages to the public.
9. Insurance.
a. TENANT shall at its own expense procure and maintain general liability and
casualty insurance in a company or companies authorized to do business in the
State of Iowa, in the following amounts:
Type of Coverage
Comprehensive General (or Premises) Liability - Each Occurrence $1,000,000
Aggregate $2,000,000
b. TENANT'S insurance carrier shall be A rated or better by A.M. Best. TENANT
shall name the COMMISSION and the City of Iowa City, as additional insured.
TENANT shall provide fifteen (15) days notice to the COMMISSION before
cancellation of said insurance. TENANT shall provide the COMMISSION a
certificate of insurance showing compliance with this provision upon execution of
this Lease.
10. No Smoking. Smoking is prohibited in the Leased Area.
11. Termination. Except as otherwise provided herein, this Lease may be terminated, without any
penalty or further liability as follows:
a. Immediately upon written notice by TENANT in the event TENANT determines that
TENANT'S intended use of the premises is actually or constructively prohibited through
no fault of TENANT.
b. Upon thirty (30) days' written notice by either party to the other party if the other party
defaults and fails to cure such default within that 30-day period, or such longer period as
may be required to diligently complete a cure commenced within that thirty -day period.
12. Notices. Any notice, for which provision is made in this Lease, shall be in writing, and
may be given by either party to the other, in addition to any other manner provided by law, in any
of the following ways:
a. by personal delivery to the Commission Chairperson
b. by service in the manner provided by law for the service of original notice, or
C. by sending said Notice by certified or registered mail, return receipt requested, to
the last known address. Notices shall be deemed to have been received on the date
of receipt as shown on the return receipt.
(I) If to the Commission, addressed to:
Iowa City Airport Commission
Iowa City Municipal Airport
1801 S. Riverside Drive
Iowa City, IA 52246
(2) If to Tenant, addressed to:
Larry E. and Sandra S. Bell
10 Greenview Court
West Branch, IA 52358
13. Right of First Refusal. If the FAA releases the Leased Area, thereby allowing the City of
Iowa City to sell the Leased Area, and if the City of Iowa City receives an offer for sale of the
Leased Area, TENANT shall have forty-eight (48) hours to match the offer in writing.
14. Inte aig_tion. This Lease constitutes the entire agreement between the parties, and as of its
effective date supersedes all prior independent agreements between the parties related to the
leasing of the Leased Area. Any change or modification hereof must be in writing signed by both
parties.
15. Waiver. The waiver by either party of any covenant or condition of this Lease shall not
thereafter preclude such party from demanding performance in accordance with the terms hereof.
16. Successors. This Lease shall run with the Property, and shall be binding upon and inure to the
benefit of the parties, their respective successors, personal representatives, and assigns.
17. Severability. If a provision hereof shall be finally declared void or illegal by any court or
administrative agency having jurisdiction over the parties to this Lease, the entire Lease shall not
be void, but the remaining provisions shall continue in effect as nearly as possible in accordance
with the original intent of the parties.
SIGNED this day of 2009.
IOWA CITY AIRPORT COMMISSION TENANT
By: By:
Janelle Rettig, Chairperson Larry E. Bell
By:
Sandra S. Bell
Howard Horan, Secretary
Approved by
•t
City Attorney's Office
COMMISSION ACKNOWLEDGEMENT
STATE OF IOWA )
) ss:
JOHNSON COUNTY)
On this day of
, before me, a Notary Public in and for the
State of Iowa, personally appeared Janelle Rettig and Howard Horan, to me personally known, and,
who, being by me duly sworn, did say that they are the Chairperson and Secretary, respectively, of
the Iowa City Airport Commission; and by authority of said Commission, as contained in
Resolution No. passed by said Commission on the day of May, 2009,
that Janelle Rettig and Howard Horan acknowledged the execution of the instrument to be their
voluntary act and deed and the voluntary act and deed of said Commission, by it voluntarily
executed.
Notary Public in and for the State of Iowa
My commission expires:
TENANTS ACKNOWLEDGEMENT
STATE OF IOWA )
)ss:
JOHNSON COUNTY)
This instrument was acknowledged before me on
Sandra S. Bell
2009 by Lary E. Bell and
Notary Public in and for the State of Iowa
My Commission expires:
ESTATE JAV
4406.010
I
(I b 11
Begnmmg at an iron Pin found at the southwest corner of Lot 12, of Sand Lake Addition to the City of Iowa
City, Iowa, according to the plat thereof recorded in Plat Book 10 Page 23, Plat Records of Johnson County,
Iowa, 3thence N 00*37'11" E, along the west line of said Lot 12ty,
, 95.feet to an iron pin thence S Coun 1"
00
.98 feet to a Point on the northwesterly right-of-way tine of relocated Gilbert Street; thence
southwesterly, 69.31 feet, along said northwesterly right-of-way line, on a 1095.83 foot radius curve, concave
southeasterly, whose 69.30 foot chord bears S 10°10'00" W to an iron pin found on the south line of said Lot
12; thence N 89°22'49" W, 119.81 feet, to the point of
said Sand bake Addition and the W beg nuing, all in accordance with the recorded plat of
County, Iowa, subject to easements and restricttionssoofr� in Book
' at page 298, Deed Records of Johnson
Prepared by: Susan Dulek, Assistant City Attorney, 410 E. Washington St., Iowa City, IA 52240 (319) 356-5030
RESOLUTION NO.
RESOLUTION SETTING A PUBLIC HEARING FOR JUNE 18, 2009,
REGARDING THE INTENT TO ENTER INTO A GROUND LEASE
AGREEMENT WITH MERSCHMAN SEEDS, INC.
WHEREAS, the City of Iowa City, the Iowa City Airport Commission, and
Merschman Seeds, Inc. entered into a Lease for an accessway from Mormon Trek Blvd.
and the centerline of the southern end of runway 18/36 at the Iowa City Airport ("Leased
Premises") for the period of March 1, 2008 to February 28, 2010; and
WHEREAS, Merschman wishes to extend the lease term by two years.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF IOWA CITY,
IOWA, THAT:
1. The Iowa City Airport Commission does hereby declare its intent to enter into the above -
referenced amendment to the lease agreement.
2. A public hearing on said proposed amendment to the lease agreement should be and is
hereby set for June 18, 2009 at 6:00 p.m. in the Terminal Building, Iowa City Airport, 1801 S.
Riverside Drive, Iowa City, Iowa, or if said meeting is cancelled, at the next meeting of the
Airport Commission thereafter as posted by the City Clerk. The City Clerk is hereby directed to
cause Notice of Public Hearing to be published as provided by law.
Passed and approved this day of
ATTEST:
SECRETARY
2009.
CHAIRPERSON
Approved by
�'� 9' — r g- - ex)
City Attorney's Office
Resolution No.
Page 2
It was moved by
adopted, and upon roll call there were:
and seconded by
the Resolution be
AYES: NAYS: ABSENT:
Farris
Gardinier
Horan
Rettig
Staley
RESOLUTION NO.
RESOLUTION AUTHORIZING THE CHAIR TO ACCEPT FAA GRANTS FOR
RUNWAY 7-25 RECONSTRUCT (PHASE 2) AND RUNWAY 12-30 RECONSTRUCT
WHEREAS, the Iowa City Airport Commission has previously applied for Federal Aviation
Administration aid in airport related projects;
WHEREAS, the Federal Aviation Administration is expected to offer grant(s) to provide funding
for the above stated projects; and
WHEREAS, it is in the best interest of the Iowa City Airport Commission to accept these grants.
NOW, THEREFORE, BE IT RESOLVED BY THE AIRPORT COMMISSION OF THE
CITY OF IOWA CITY:
1. The Chairperson is authorized sign and the Secretary to attest to acceptance of FAA
grants related to the above mentioned projects.
Passed and approved this
CHAIRPERSON
ATTEST:
SECRETARY
day of
Approved By:
City Attorney's Office
It was moved by and seconded by
Resolution be adopted, and upon roll call there were:
Ayes
Nays
Absent
Farris
Gardinier
Horan
Rettig
Staley
the
Prepared by: Michael Tharp, Operations Specialist, 1801 S. Riverside Dr, Iowa City IA 52246 319-350-5045
RESOLUTION NO.
RESOLUTION AWARDING CONTRACT AND AUTHORIZING THE
CHAIRPERSON TO SIGN AND THE SECRETARY TO ATTEST A CONTRACT
FOR THE RECONSTRUCT RUNWAY 7-25 (PHASE 2) AND RECONSTRUCT
RUNWAY 12/30 PROJECT.
WHEREAS, Metro Pavers, Inc. of Iowa City, Iowa has submitted the lowest responsible bid of
$3,413,671.50 for construction of the above named project.
NOW, THEREFORE, BE IT RESOLVED BY THE IOWA CITY AIRPORT COMMISSION, THAT:
The contract for the construction of the above named project is hereby awarded to
_Metro Pavers, Inc._ subject to the condition that awardee secure adequate
performance and payment bond, insurance certificates, and contract compliance
program statements and that the Commission secure FAA grant funding.
2. The Chairperson is hereby authorized to sign and the Secretary to attest the contract for
construction of the above -named project, subject to the condition that awardee secure
adequate performance and payment bond, insurance certificates, and contract
compliance program statements and subject to the Commission receiving financing.
Passed and approved this day of 12009.
CHAIRPERSON
ATTEST:
SECRETARY
It was moved by
adopted, and upon roll call there were:
Ayes
and seconded by
Nays
Approved by
rB--�S
City Attorney's Office
Absent
the Resolution be
Farris
Gardinier
Horan
Rettig
Staley
AECOM
AECOM
500 SW 7th Street, Suite 301, Des Moines, Iowa 50309
www.aecom.com
May 7, 2009
Ms. Janelle Rettig
Iowa City Airport Commission
1801 S. Riverside Drive
Iowa City, IA 52246
SUBJECT: Reconstruct Runway 7/25 (Phase 2) and
Reconstruct Runway 12/30
Iowa City Municipal Airport
City of Iowa City, Iowa
FAA AIP Project Nos. 3-19-0047-17, 18, & 19
AECOM ID No. 110563 and 111879
Dear Ms. Rettig:
We have reviewed the bids received by the City of Iowa City on April 29, 2009, for the above -
mentioned project. No errors or inconsistencies were found in any of the bids during the bid review. A
copy of the bid tabulation is attached.
Two (2) bids were received. Metro Pavers, Inc. of Iowa City, Iowa, submitted the low bid in the amount
of $3,413,671.50. The low bid submitted was lower than the Engineer's Estimate by an amount of
$1,470,150.50. Metro Pavers, Inc. indicated in their bid that they were able to meet the DBE goal of
10% as specified in the bid documents. They committed to a minimum of 10.62% DBE utilization on
this contract.
In addition to the above review and tabulation of bids, we requested documentation from Metro Pavers,
Inc. regarding the amount of work that they planned to sublet. Based on the information received,
Metro Pavers, Inc. currently plans to sublet $2,036,741.40 or 59.7% of the project and will perform
$1,376,930.10 or 40.3% of the project directly. This meets the requirement set forth in Section 80-01 of
the General Provisions of the Specifications.
We recommend award of a contract for Reconstruct Runway 7/25 (Phase 2) and Reconstruct Runway
12/30, FAA AIP Project Nos. 3-19-0047-17, 18, & 19 to Metro Pavers, Inc. of Iowa City, Iowa, in the
amount of $3,413,671.50, subject to FAA concurrence.
If you should have any questions or need additional information, please contact our office at your
convenience.
Yours sincerely,
Z " 3. ��.
David B. Hughes, P.E.
Enclosures: As noted
cc: Mr. Donald Harper, Federal Aviation Administration (w/enclosures)
LAw Mpmje U 1056sW.nUmmWR050709.1V.d=
T¢Eulauon OlBo.
Ramm4uNon
01 Ru maa y 7d5 (pn..e
2)
eO
RecOn clicn12J0
bwe DIVWrlN "Ak
MW,i Abytl
1 Iowa COy.laae
FAA Alp
No 11-fL10619
N0,
AELOM Pmect 10 6111B)8
Apfi
ApNI 30, 2009
nBnvv v
Esman.
Oil. Pave]e. Nc.
StreO Conmuccom Company. Inc,
REA1
Ion ED, 1.
1. CIIY.Iowa
NO.
SPEC NOOESCRIPTION
UNIT
ESTMAWD OW]RRY
UWCOST
ESTIMTED
COST
UNnT COST
ESTNWTEOCOST
UNT COST
ESTIMATED COST
OMslonl
pMslon ll
Tdal
gNSIOnI
pMilonp
Tdal
pM¢IOnI
DWSWIS 1
Y.
DIN]Ivnl
DiW51Mll I
Tonal
1
2
P-100q.I
GP!s
MMiRalvrnM Cumobc.l..
COMruggnfiury
LS
OS
I S1
1
3$SOOW.Op
S1Z90W00
H35.OpOW
j3500.tl.00
fI5f,OW.Op
51880000
S]6.80000
516 .BWOO
33W,CW.W
E1]B W].00
E1]5.000 pJ
$SSO WOW
J
P-ID2E.1
Pwerrenl Renwvol
LS
0.5
05
I
S)O WOW
535 WO.W
f35,OW 00
flO W0.00
$]H.B[O 00
$1B<50.00
E19 <SO.W
$SB,B00.00
$dp.W000
510 CW'.00
g30,000W
Sa00W 00
1
P-103-52
Runw+En eLI M1l Removvl
SYO
47SW
400B0
BSbW
3]50
31GG }50.00
j1fi0,9500
3]JI d3306
g2.15
f103125.W
51W 30]50
$RO LRW
$R.16
E102115.00
EID330?60
f305 dS250
8
P-1035.3EKKBIaIXpntlM1ola
flomoval
EA
EA
S9
]d
f]5W
283SW
f2.935.00
5650W
$BSW
R9]BW
$3]1500
SRBOW
$8500
E2B15,00
$3315W
5839000
e
P.1035.I
SIorm Sever gemvvpl
LFT
1.
1fi
5000
p
1B
$]500
H OW
gOW
f1350W
HSW
SB10W
50,00
f01OW
E45W
fB10W
§0.0p
$H)p Op
P-1WSS
Slum Svwr61ru6un Rarmvel
Eq
J1
RBW
14
B)W
516.00
f01 OW
51],SW.W
g1305WPo
SS.00
SN BWW
31I,aWW
SYI,ZWW
HW
5232W Iq
f11 WOW
531800.W
B
P-152�1
Vrtlm¢YivG Ei-�alun
CYO
235W
BHW
]6
31 WJAp
331 00
H4ppp p3
j)B.OW.W
$300W
$10IWW
313.iW,W
323aW00
'jI65W
f46fOW
$1.26p.W
SI}OIOW
0
p-152<]LVC
0aNi0
CYD
R
HM
IW 0.UW
$332WW
H1B2W.W
$2]0
H95W,W
$RISW.W
3]10W.00
$220
H9.SWW
$315W.W
E>I WOW
10
P-152-0]Orvi
Eirnvlwr OOpr Grant
5 c
57.W
f30.650Ap
f3}1W,W
f11050.
3311p
5106W 0]
EtSbCO.W
SN550.W
g]W
SIB650.W
ft].BW pp
3]OASOAp
11
Poam
Gedenib
{FT
6YD
LFT
LFT
LFT
300W]W
BWp
pS0MDOS.1700
0.
eW000p
050
W0
W0
$25W
5).W
j},W
51.60
521 },Sp,W
511 B.Lp00
512,OW.W
E90W.00
gO.W
51W6WW
512,WO.W
f90W Op
331250.W
$3W W0.00
5}10.U.00
3100.'V.00
$8.00
32.51
$}.30
E050
$SIWO]
fl04WAp
138WW
f3W000
$O.W
Sfi5,53$.W
513 WO.W
f3WJ.00
15100W
f144.O1BW
52)6W.W
WO.W
fOW
fR2p
$230
E1W
IS.1W pJ
SB)9W 0]
fl]BOOW
Hp00W
SOW
550.)fi0W
g1]BW.W
EB W3.00
SS1W.W
H2d,]a000
f316Po.W
f13 WOW
12
P-ISeb1
Sa Famo
13
P-I5fib.2
Cbv nnE Railorpllvnd Im Fen-
10
P-15Bd351n
Fenm gemwvl
10
P.}IB5.1
Ro ckd CanweleA re vle ban Coune
6YD
j1.W
j9 W30]
f90W.00
f1B W000
b005
SS Do
ESIW.pO
iIOZWW
$005
53100 pp
ES 1W.00
g10 R00W
1B
PA0f8f
PorllannCemenl cm-10-O'T,.Im...
Ponlantl Lemenl Concele-e'ID¢kneae
6Y0
6YD
TON
SYO
SFT
MO I:o)00
]WO42p
H550650
BODD
aB000MA
2.=
1B.900
18,11p
H.]5
$20W
f3OW
5130.W
53W
f035
Std6 )]500
32212W 0p
Sfi4B5W 00
f10.W0W
390 CO
E12I,i5000
f688.56000
SOW
$OW
SOW
20932500
SWI]6pPo
f840500W
S10 WOW
S..Am.W
S2 i9
23]55
$29.In
SIfiOan
a,11
$)6,)05.
-----3
1. ]ISW
S154WPo
$.5 Snoc
$0W
$OW
SOLO
Iel9 ]25W
f1 ANGo
f651W.W
E2]50
$INDO.
$150
y59282500
S1a1W.00
S12.00 W
SOD.5592025W
au
fOW
SIg4W1B
313 pppW
S2,MDO
V
Pb01d3
10
PZU1-03
A¢Ba4 Trvntllon Pwomenl
P
flummt D
ZO
Pd1051
041
qu Ma .Xe ge9MNe
21
Pd20.a3R
MaM1L eMw Re!k[Ihv
SFF
IW
EI8,1$SW
f14.9ISM
fNB50.W
11.55
f40.]65.W
$SOAISW
3118fOW
$155
3<0165W
SSO.HiW
22
PLAS3
Ru `A vclrve
SFT
SBW
350
3)W
)60
93W
10]
faWW
f3A.W
f]50.
f1 H5
00
f5]]50
f133]W
it ES
WW
f5»W
$12]]Do
3]
PA$p6A
Ru MOM1r ra
i .amcam,
SFT
4W0
0
40W
$075
511WW
sz,mpo
HB]SW
1135
"nor CO
H025.m
$11535W
5135
f)WOW
$4615W
SI1025W
21
0.ID1d.110{ntlr
pemlvrmO Comele Pi qL
LFT
IFT
434
SBl
.1
1375
U.W
E45W
$92W [U
51990W
sow
f12.3i5.W
59.200W
Efif 815W
32.25
S}?W
j10 J500p
31111Op0
§pOJ
$2540700
$IOJSp,W
$3712500
y225
$2200
310.]50W
W.Soo
f000
330]0200
SIp.J50.W
33 IWOO
24
0.]015.$21{non
gein!onwn Conuolo Pie RCP
3B
0.]O,SJ
30IncB gelnfor-E Lonucle Pi v RCP
LFT
404
1,01]
1110
1B]4
SSiPo
fJ2815W
$59)SSW
j920I0.W
5]3.W
318 )01.00
E35.H1.00
521$p0
$3800
$10)1000
f30,15000
540,0]2.W
2]
D]01aa,
-Inch.- P ul R elnlo2etl Concrele Arul PIe RLP
Rainlometl Corrcmla NN PI 0.CP
NHnM Reinlor-S Covucle Pl RCP F1vre0EnX Hetlbn
LFT
LFT
EA
Ea
LFT
IBO
0
0
0
6JW
0
LASS
1
t
5&U
1514
We
} AB
1
1
11150
$)0.00
WDED
$95.00
12LCO.W
125CO.W
$2B28000
$1470000
$0.00
SOW
SOW
$81900.W
$000
4346.B10Ap
g20W.00
525WW
11f01B000
314 ]W.00
f218 B10.00
53.([O.W
32 OD
Sa3.W
$SBW
AS.W
$950W
512WW
31131R00
310.8]500
W
E000
5000
E5031000
bOW
$194,6`A.W
$9W.p0
Et W.Do
f610020
$t 9>800
$194 BWW
$950W
St I.
$3600
12.11
$R00
f1,0W.W
S1mo
51151400
$12.152,00
f000
$000
$0.
14212.A
sum
f181,O5fi 00
$,.BWW
$I,OW 00
$58664
H2t5]W
f1B?OSSW
SI,BWM
tt aWW
2B
0.)015414{ncfi.2)Inclr
29
0.)OIES
30
0.]0156
U{vyra 2]Incn ReinlomN Cormle A a;12 qC tCron EM 5"an
Slog Perlon!M SUMain Oq 15 Mlgi Bvckf
]1
0.]0561
]2
0.]OSfi3
BiM WnLMualetl SUBLrein OR ]5
LFT
610
e20
SBW
i42.0W.W
H8,<W,W
S99 WW
fB JS
H4fiT150
HS430.W
3931DI an
$8]5
S""N SO
H)8SJ LID
f919B150
3]
0.1055]SUMnIn
Cbvmul
Eq
3$
10
t4B
SMOD
H130W
59040.00
515 WO.W
fS.W
fJ,315W
f5330.pp
fBH45W
T535
j]IB1W
55125.00
SB,313.W
a
0.]5151
.erin:ake!mR;NG
EA
6
ffiW.W
j1BCHOW
HO.PIpW
j3I6W,W
$SOOW
$14.W0.W
$OWD.00
32.,Do
f3]0W
f1560W
HBWW
512a30W
JS
0.)51d251um5awerinlpkefor
Amarn ArtlrRe
FA
]
B
15
$l.W]W
S1B,WO,W
E2]OOp.W53,200W
.1.1WW
$Ze.OW.W
HCW 00
330.'O.W
YtO WOW
$2),WJ.00
$45,000W
]0
T.W1-S.I
Sae6N vn0 Mu4M1i
gCRE
2B
9
13
11
fSCW.W
Hp WOW
§d5 p0000
f55 WO,00
H2O0W
04W00
E3]80000
H2WW
$4001
S&WODo
S. MSC
$44000W
TA01.5281p611Rin
Cm
ACRE
20
13
41
$3,SW.W
$1.1b00.00
H2,000.d1
31435W.00
.1 DO
33O1WW
$10,300 00
555350.00
$1 ]50,00
E]915000
j18.300.00
Y55 ]5000
3
30
TA055.1
To vllin-OEIaInvtl OrrSXa
CYO
3a000
B.Wp
dt
32
§Bp0.00
j2]300.00
59 fi00.00
j]2BW,00
$SHOOp
SIfi B20W
$fi9W 00
$ZJ )8004
SSW.00
f10 B2000
E896000
$2])00.D0
JB
L1064t
No.0AN'GL-02<C LoOle lnsleAa81n T1pren pucl Bany of ConOUA
LFT
15000
0
ppp
SSW
$12000000
HISW 00
S1H W0.00
Y3.R5
f]B WOW
$28.925.00
$1 939W
$]35
A0,00000
42BB2500
2000
f100B25W
40
H ANp GnonlnwYleS GmuM ingaAM In Trvmlr
LFT
2W0
0
15000
42.50
$3)Wp00
YOW
E]1 0W
$Og0
S135W.W
E0W
f1350000
W90
5135W 00
S1JW0W
11
".3No.
L-,W53
111P5.1
Nv.BAY1C2 Rpn Cum, InWakNNinrcM1
E6clrvlLOMuA 2lntlr PVC. SCZatuly a0
LFT
LFT
t]SW
1].BW
0
0
20W
1].BW
f3W
f2W
WMIUOp
SN.SW.W
§9W
$O.W
fBCWW
3345W.W
f]60
ft.)0
3)2WW
S]],aBpW
U.
fODo
3)20OW
f13.a80W
W.
51.]0
Il]W 00
3}]4WW
SO,W
so.
S?iWW
123 aWW
4]
4]
L11P52
ElGreplCupup 21rch PVC, 6tlrW UY80 NINE'S
LJB1MNrumin!em Runv2 Evv M nm'IhTla Ler¢
LFT
FA
2W
23
0
0
t3BW
2W
2M.
j1OW
I69.CM.SO
HCW.W
WW
50.W
SfiLOW.W
H0.V.W
y].W
311.W
H1400W
32 P4O,W
WO
SO.W
M.WW
328WW
33W
514W
Hf aWW
S}BWW
WW
$O.W
541LWW
f3.BW.W
44
LA1551
IS
L13S52
LS91 Med,u minlem qu EB eL M ilWellow Lcm
MCElumintem flurma EE LIMGrvoNfle6 Lana
Eq
EA
EA
Eq
]1
18
f0
30
0
0
0
0
3]
31
1fi
11
11 W.W
513W 00
H 000
$BW,W
53)6W.W
53],]!p.W
S1B2W.W
$11 WW
EO,W
§pW
SOW
$OW
3» W
$3I,200W
S1B200W
E112WW
S120W
$]]p.00
H2500
$fi3000
31BSWW
123630W
f1J-0000
Ev 6M 00
SOW
gOW
8000
$000
$1SSWW
f2 W000
51330000
U,.2.00
$RD.W
f]30.00
503500
$fi3000
f,A...
31B SSOW
ft]2W 00
gB 63000
SOPo
SOW
EOW
SOW
fi0560W
".SOO,
513300W
$B BlOW
IB
L12S5]LEO1
4)
.125
LSfi0Elvdnml XvnEFp4e
40
So
GRS95
Ld53 gvlmmevclhe Marterw.In SOA pncM1u
JO
E125W
]>60W
0.00
)SO pO
$9000
32)W00
E000
33 )W.W
$90W
$2]W00
§OW
$2100W
wa, minc,DNOIonIPM hw nl
2,fi5G 140W S11BI.fi90.
,p0] W
SIO O.GW.SO H533.I>f.
341H0]150
31B 4WW f1.H2562W 534<$9H2p0
DOE
DO
SIDE
10.52%
OSE
B01%
Prepared by: Michael Tharp, Operations Specialist, 1801 S. Riverside Dr. Iowa City, IA 52246 (319) 350 5045
RESOLUTION NO.
RESOLUTION APPROVING TASK ORDER NO. 3 WITH AECOM FOR
ENGINEERING CONSTRUCTION SERVICES RELATING TO THE RUNWAY 7-25
AND RUNWAY 12-30 RECONSTRUCTION
WHEREAS, the Iowa City Airport Commission entered into a contract entitled "Professional
Services Agreement" with Earth Tech on December 11, 2008 to provide engineering services
Federal Airport Improvement Program Projects;
WHEREAS, Part I(A) of said agreement provides that the parties will enter into supplemental
agreements for each project;
WHEREAS, the Commission and AECOM have previously entered into Task Order Nos. 1 and
2;
WHERAS, the Commission and AECOM now desire to enter into Task Order No. 3, a copy of
which is attached; and
WHEREAS, it is in the best interest of the Commission to enter into Task Order No. 3
NOW, THEREFORE, BE IT RESOLVED BY THE AIRPORT COMMISSION OF THE
CITY OF IOWA CITY:
1. The Chairperson is authorized to sign Task Order No. 3 after concurrence with FAA.
Passed and approved this day of 2009.
CHAIRPERSON
ATTEST:
SECRETARY
It was moved by and seconded by
adopted, and upon roll call there were:
Ayes
Nays
Approved By:
City Attorney's Office
Absent
the Resolution be
Farris
Gardinier
Horan
Rettig
Staley
AECOM
AECOM
501 Sycamore Street, Suite 222, Waterloo, Iowa 50703
T 319.232.6531 F 319.232.0271 www.aecom corn
TASK ORDER NO. 3
REHABILITATION OF RUNWAY 7-25 AND RUNWAY 12-30
IOWA CITY MUNICIPAL AIRPORT
IOWA CITY, IOWA
FAA PROJECT NO.3-19-0047-17 AND 18
Project Description - See attachment and incorporated herein.
Scope of Services - See attachment and incorporated herein.
Compensation
A. Compensation for services for the Construction Phase shall be a cost plus fixed fee not -to -exceed
Two Hundred Seventeen Thousand Dollars ($217,000.00). See attachment and incorporated
herein.
General Conditions
Except as specifically amended by this agreement, services shall be provided in accordance with the
Consultant Services Agreement for the Iowa City Municipal Airport between AECOM Technical Services,
Inc., and the Iowa City Airport Commission dated December 22, 2008.
APPROVED
IOWA CITY AIRPORT COMMISSION
L:\work\ADMIN\AGREE\PROF\ICAirportTaskOrder3.doc
APPROVED
AECOM TECHNICAL SERVICES, INC.
By
Joe A. Becker
Date May 7, 2009
SCOPE OF SERVICES
FOR
REHABILITATION OF RUNWAY 7-25 AND RUNWAY 12-30
IOWA CITY MUNICIPAL AIRPORT
IOWA CITY, IOWA
FAA AIP 3-19-0047-17 & 18
Project Description
The project is described as the Rehabilitation of Runway 7-25 and Runway 12-30 at the Iowa City
Municipal Airport, Iowa City, Iowa. The project includes approximately 1,850 feet of Runway 7-25
that remains between the work completed on AIP Project No. 3-19-0047-14 and on AIP Project
No. 3-19-0047-16. The project includes approximately 1,400 feet on the north end of Runway
12-30 and a new runway lighting system for Runway 12-30. The intersection of the two runways
(7-25 and 12-30) is a part of this project. The rehabilitation will be accomplished by
reconstruction of the existing runways with Portland cement concrete pavement with grooving
and marking. The work involved in the project will also include pavement removal, excavation,
aggregate base course, storm sewer, subdrain, runway edge lighting, and surface restoration.
The project will be funded by federal Airport Improvement Program funds.
It. General Project Scope
The work to be performed by the Consultant shall encompass and include detailed work,
services, materials, equipment and supplies necessary to provide construction phase services.
The design phase has been completed and the project has been bid. The construction phase
services shall be divided into the following tasks:
A. Construction Phase
1. Assignment of Construction Manager. This task consists of assigning a
project engineer who will coordinate Project activities and will be the principal
liaison between the Sponsor, Consultant and regulatory agencies.
2. Assemble Construction Documents. This task consists of assisting the
Sponsor in assembling the contract documents for execution by the Contractor
and the Sponsor.
3. Pre -Construction Conference. This task consists of attending and conducting
a pre -construction conference with representatives of the Contractor, Sponsor,
Consultant, FAA and affected utilities.
4. Construction Surveying. This task consists of establishing horizontal and
vertical control for the project. In addition, this task includes checking the
Contractor survey notes for accuracy and method of staking. Contractor's survey
will be checked on a weekly basis, prior to beginning work in the area staked,
and periodically for grade and alignment. The survey notes received from the
Contractor will be organized, checked, and filed for reference during the project.
5. Shoo Drawings and Submittals. This task consists of reviewing shop drawings
and other submittals as required of the Contractor by the contract documents for
conformance with the design concept of the Project and compliance with the
information given in the contract documents.
Page 2
6. Construction Observation Program. This task consists of preparation of
Construction Observation Program which will detail the measures and
procedures that are required to assure conformance with the approved plans and
specifications. This program will be developed in accordance with the FAA
Central Region AIP Sponsor Guide.
7. Construction Assistance. This task consists of answering design interpretation
questions from the Sponsor, Contractor, review staff and appropriate agencies.
8. Pay Applications. This task consists of preparing and processing monthly
applications for payment to the Contractor and forwarding to the Sponsor for
execution with recommendations for approval and payment.
9. Labor and Payroll Reports. This task consists of the reviewing weekly labor
and payroll reports for compliance with Davis -Bacon Act, conducting on -site
employee interviews, and conducting E.E.O. site inspections. Original
documents will be submitted to the Sponsor at completion of project for storage.
10. Testinq of Materials. This task consists of providing field testing and materials
testing in accordance with the Construction Inspection Program. A subconsultant
will provide quality assurance testing for establishing Proctor values for the base
rock and embankment materials and provide acceptance testing for Asphaltic
cement concrete pavements.
11. Site Visits. This task consists of providing periodic site visits to the construction
site by design personnel at appropriate stages of construction to review the
quality of the work and to determine, in general, whether the work conforms with
the contract documents.
12. Change Orders. This task consists of coordinating with the Sponsor and
Contractor in preparing and processing contract change orders.
13. Pre -paving Conference. This task consists of a meeting with the contractor,
quality assurance testing lab, resident project representative and the project
manager to discuss the testing requirements and paving plan for the runway
extension to assure that controls are in place to meet the project specifications
prior to beginning paving operations.
14. Construction Observation. This task consists of providing field observation
during construction to review the work of the Contractor to determine if the work
is proceeding in general accordance with the contract documents and that
completed work appears to conform to the contract documents. Also included in
this task will be the monitoring of DBE participation in the project. Staffing
requirements may be adjusted during the Project in relation to the level of
construction activity.
15. Intersection Closure Coordination. This task consists of meeting with the
Airport staff, tenants, and the Contractor for weekly progress meetings during the
construction phase of the project that requires closure of the airfield. The
meeting is to discuss project progress, safety, operations, construction issues,
and identify upcoming construction schedule. These meetings are required to
minimize the time that the airfield will be closed to air traffic.
Page 3
16. Non -Compliance Reporting. This task consists of reporting to the Sponsor any
work believed to be unsatisfactory, faulty or defective or does not conform to the
contract documents, and advising the Sponsor of any work that should be
corrected or rejected.
17. Contractor Modifications. This task consists of reviewing, evaluating and
making recommendations to the Sponsor on suggestions for modifications that
have been made by the Contractor.
18. Proiect Files. This task consists of maintaining files for correspondence, reports
of the job conferences, shop drawings, and sample submissions, reproductions
of original contract documents including addenda, change orders, field
modifications, additional drawings issued subsequent to the execution of the
contract, Engineer clarifications and interpretations of the contract documents,
progress reports and other Project -related documents.
19. Daily Reports. This task consists of the resident field representative keeping a
diary, log book or report for those times on site, recording hours on the job site;
weather conditions; data relative to questions of extras or deductions; list of
visiting officials and representatives of manufacturers, fabricators, suppliers and
distributors; activities; decisions, observations in general and specific
observations in more detail when necessary, as in the case of observing test
procedures. As part of this task weekly construction progress and inspection
reports will be prepared and submitted to the FAA.
20. Punch List. This task consists of conducting a review of the Project near
completion and preparing a list of items (Punch List) to be completed or
corrected.
21. Final Review. This task consists of performing a field observation of the
completed Project before a final application for payment is processed for the
Contractor.
22. Proiect Closeout. This task consists of assisting the Sponsor with Project
completion and final closeout documentation from the Contractor for the FAA by
providing a statement covering the following.
a. Sponsor Certification for Final Acceptance
b. Final Outlay Report —Standard Form SF-271
C. Final Project Cost Summary
d. Final Construction Report
1) Brief narrative of work accomplished as well as any excluded
items.
2) Summary of key milestone dates — Receipt of Bids, NTP,
Substantial Completion, Contract Date, Final Inspection, Final
Acceptance.
3) Explanation of liquidated damages (if required).
4) Statement of compliance with contract labor provisions (payroll
reviews, complaints, etc.) Reference AC 150/5100-6.
5) Summary of final contract quantities.
6) Explanation of underruns and overruns.
7) Change Order Summary.
Page 4
8) Testing Report Summary including a copy of all acceptance test
results.
9) Final Inspection Report including signature of consultant.
10) Contractor's Final Statement of Completion — typically submitted
as the final payment request.
e. Summary of DBE Utilization
23. Record Drawings. This task consists of providing the Sponsor with a copy of Record
Drawings of the construction plans for the Project based on the construction observation
records of the review staff and Contractor showing those changes made during
construction considered significant. Two copies of the Record Drawings in electronic and
reproducible format will be provided to the Sponsor. One electronic copy would be for
the FAA. Electronic drawings shall be in MicroStation V8 format. Task does not include
updating of the Airport Layout Plans.
24. Proiect Administration. This task consists of office administration and coordination of
the project. Interoffice meetings, general day-to-day administrative responsibilities, and
typing of interoffice memoranda and minutes of meetings are included in this task.
L:\work\ADMIN1AGREE\PRORICTaskOrder3Scope.doc
IV.
V.
Rehabilitation of Runway 7-25 & Runway 12-30
Iowa City Municipal Airport
Iowa City, Iowa
FAA Project No. 3-19-0047-17 & 18
CRS Services
Consultant Cost Summary
Direct Labor Cost
Category
Hours
Rate/Hour
Senior Professional
52
$79.00
Project Professional
264
$64.00
Staff Professional
168
$37.00
CADD Operator
60
$25.00
Senior Technician
850
$29.50
Technician
494
$22.00
Project Support
116
$19.50
2004
Payroll Burden and Overhead Provisional Costs
Direct Project Expenses
Amount
$4,108.00
$16,896.00
$6,216.00
$1,500.00
$25,075.00
$10,868.00
$2,262.00
165.00%
$66,925.00
$110,426.25
Category
Units
Rate/Unit
Amount
Mileage
2200
0.550
1,210.00
Per Diem
0
30.00
0.00
Lodging
0
55.00
0.00
Copier
1400
0.06
84.00
Plan Copier
170
0.50
85.00
GPS
55
25.00
1,375.00
Geodimeter
66
12.50
825.00
Miscellaneous, Other
500.00 $4,079.00
Earth Tech Estimated Actual Costs
Subcontract Expense
Terracon. - Testing Services
Estimated Actual Costs
Fixed Fee
Maximum Amount Payable
Rounded
$181,430.25
$181,400.00
$190,400.00
$26,600.00
$217,000.00
Rehabilitation of Runway 7-25 & Runway 12-30
Iowa City Municipal Airport
Iowa City, Iowa
FAA Project No. 3-19-0047-17 & 18
CRS Services
Staff Hour Estimate
Item
No.
Description
Senior
Prof
Project
Prof
Staff
Prof
CADD
Operator
Senior
rechniciarTechniciar
Project
Support
Totals
1
Assignment of Construction Manager
0
2
Assemble Construction Documents
4
8
8
20
3
Pre -Construction Conference
2
2
4
4
Construction Surveying
136
136
272
5
Shop Drawings and Submittals
12
16
12
40
Construction Observation Program
16
8
24
6
Construction Assistance
8
100
40
148
7
Pay Applications and Reimbursements
10
10
8
Labor and Payroll Reports
40
40
9
Testing of Materials
8
8
16
10
Site Visits
8
16
8
32
11
Change Orders
4
6
16
12
4
42
12
Pre -Paving Conference
4
4
6
14
13
Construction Observation
610
320
930
14
Intersection Closure Coordination
80
80
15
Non -Compliance Reporting
4
4
8
16
Contractor Modifications
4
4
8
17
Project Files
24
24
18
Daily Reports
72
32
104
19
Punch List
2
4
8
14
20
Final Review
2
4
8
14
21
Project Close-out
8
12
24
12
8
64
22
Record Drawings
8
16
40
64
23
Construction Administration
20
12
32
Total Construction Phase Services
1 52
264
168
60
850
494
116
2 004
Prepared by: Michael Tharp, Operations Specialist, 1801 S. Riverside Dr. Iowa City, IA 52246 (319) 350 5045
RESOLUTION NO.
RESOLUTION APPROVING TASK ORDER NO. 4 WITH AECOM FOR
ENGINEERING CONSTRUCTION SERVICES RELATING TO THE RUNWAY 12-30
RECONSTRUCTION
WHEREAS, the Iowa City Airport Commission entered into a contract entitled "Professional
Services Agreement" with Earth Tech on December 11, 2008 to provide engineering services for
Federal Airport Improvement Program Projects;
WHEREAS, Part I(A) of said agreement provides that the parties will enter into supplemental
agreements for each project;
WHEREAS, the Commission and AECOM have previously entered into Task Order Nos. 1-3;
WHERAS, the Commission and AECOM now desire to enter into Task Order No. 4, a copy of
which is attached; and
WHEREAS, it is in the best interest of the Commission to enter into Task Order No. 4
NOW, THEREFORE, BE IT RESOLVED BY THE AIRPORT COMMISSION OF THE
CITY OF IOWA CITY:
1. The Chairperson is authorized to sign Task Order No. 4 after concurrence with FAA.
Passed and approved this
CHAIRPERSON
ATTEST:
SECRETARY
day of
It was moved by and seconded by
adopted, and upon roll call there were:
Ayes
Nays
2009.
Approved By:
City Attorney's Office
Absent
the Resolution be
Farris
Gardinier
Horan
Rettig
Staley
AECOM
AECOM
501 Sycamore Street, Suite 222, Waterloo, Iowa 50703
T 319.232.6531 F319.232.0271 www.aecom.com
TASK ORDER NO. 4
REHABILITATION OF RUNWAY 12-30
PHASE 11— FAA ECONOMIC RECOVERY FUNDS
IOWA CITY MUNICIPAL AIRPORT
IOWA CITY. IOWA
FAA PROJECT NO. 3-19-0047-19
Project Description - See attachment and incorporated herein.
Scope of Services - See attachment and incorporated herein.
Compensation
A. Compensation for services for the Construction Phase shall be a cost plus fixed fee not -to -exceed
One Hundred Sixty -Seven Thousand Dollars ($167,000.00) See attachment and incorporated
herein.
General Conditions
Except as specifically amended by this agreement, services shall be provided in accordance with the
Consultant Services Agreement for the Iowa City Municipal Airport between AECOM Technical Services,
Inc., and the Iowa City Airport Commission dated December 22, 2008.
APPROVED
IOWA CITY AIRPORT COMMISSION
L:%workW DMINVAGREEIPROFtICTaskOrder4.doc
APPROVED
AECOM TECHNICAL SERVICES, INC.
By ��
Joe A. Becker
Date May 7 2009
SCOPE OF SERVICES
FOR
REHABILITATION OF RUNWAY 12-30 (PHASE 2)
IOWA CITY MUNICIPAL AIRPORT
IOWA CITY, IOWA
FAA AIP 3-19-0047-19
Project Description
The project is described as the Phase 2 of Rehabilitation of Runway 12-30 at the Iowa
City Municipal Airport, Iowa City, Iowa. The project includes approximately 2,500 feet of
Runway 12-30 that remains south of the work completed on AIP Project No. 3-19-0047-
17 and 3-19-0047-18. The rehabilitation will be accomplished by reconstruction of the
existing runways with Portland cement concrete pavement with marking. The work
involved in the project will also include pavement removal, excavation, aggregate base
course, storm sewer, subdrain, and surface restoration. The project will be funded by
federal Economic Recovery funds.
II. General Project Scope
The work to be performed by the Consultant shall encompass and include detailed work,
services, materials, equipment and supplies necessary to provide construction phase
services. The design phase has been completed and the project has been bid. The
construction phase services shall be divided into the following tasks:
A. Construction Phase
1. Assignment of Construction Manager. This task consists of assigning
a project engineer who will coordinate Project activities and will be the
principal liaison between the Sponsor, Consultant and regulatory
agencies.
2. Assemble Construction Documents. This task consists of assisting
the Sponsor in assembling the contract documents for execution by the
Contractor and the Sponsor.
3. Pre -Construction Conference. This task consists of attending and
conducting a pre -construction conference with representatives of the
Contractor, Sponsor, Consultant, FAA and affected utilities.
4. Construction Surveying. This task consists of establishing horizontal
and vertical control for the project. In addition, this task includes
checking the Contractor survey notes for accuracy and method of
staking. Contractor's survey will be checked on a weekly basis, prior to
beginning work in the area staked, and periodically for grade and
alignment. The survey notes received from the Contractor will be
organized, checked, and filed for reference during the project.
Page 2
5. Shop Drawings and Submittals. This task consists of reviewing shop
drawings and other submittals as required of the Contractor by the
contract documents for conformance with the design concept of the
Project and compliance with the information given in the contract
documents.
6. Construction Observation Program. This task consists of preparation
of Construction Observation Program which will detail the measures and
procedures that are required to assure conformance with the approved
plans and specifications. This program will be developed in accordance
with the FAA Central Region AIP Sponsor Guide.
7. Construction Assistance. This task consists of answering design
interpretation questions from the Sponsor, Contractor, review staff and
appropriate agencies.
8. Pay Applications. This task consists of preparing and processing
monthly applications for payment to the Contractor and forwarding to the
Sponsor for execution with recommendations for approval and payment.
9. Labor and Payroll Reports. This task consists of the reviewing weekly
labor and payroll reports for compliance with Davis -Bacon Act,
conducting on -site employee interviews, and conducting E.E.O. site
inspections. Original documents will be submitted to the Sponsor at
completion of project for storage.
10. Testing of Materials. This task consists of providing field testing and
materials testing in accordance with the Construction Inspection
Program. A subconsultant will provide quality assurance testing for
establishing Proctor values for the base rock and embankment materials
and provide acceptance testing for Asphaltic cement concrete
pavements.
11. Site Visits. This task consists of providing periodic site visits to the
construction site by design personnel at appropriate stages of
construction to review the quality of the work and to determine, in
general, whether the work conforms with the contract documents.
12. Change Orders. This task consists of coordinating with the Sponsor
and Contractor in preparing and processing contract change orders.
13. Pre -paving Conference. This task consists of a meeting with the
contractor, quality assurance testing lab, resident project representative
and the project manager to discuss the testing requirements and paving
plan for the runway extension to assure that controls are in place to meet
the project specifications prior to beginning paving operations.
14. Construction Observation. This task consists of providing field
observation during construction to review the work of the Contractor to
determine if the work is proceeding in general accordance with the
Page 3
contract documents and that completed work appears to conform to the
contract documents. Also included in this task will be the monitoring of
DBE participation in the project. Staffing requirements may be adjusted
during the Project in relation to the level of construction activity.
15. Non -Compliance Reportina. This task consists of reporting to the
Sponsor any work believed to be unsatisfactory, faulty or defective or
does not conform to the contract documents, and advising the Sponsor
of any work that should be corrected or rejected.
16. Contractor Modifications. This task consists of reviewing, evaluating
and making recommendations to the Sponsor on suggestions for
modifications that have been made by the Contractor.
17. Proiect Files. This task consists of maintaining files for
correspondence, reports of the job conferences, shop drawings, and
sample submissions, reproductions of original contract documents
including addenda, change orders, field modifications, additional
drawings issued subsequent to the execution of the contract, Engineer
clarifications and interpretations of the contract documents, progress
reports and other Project -related documents.
18. Daily Reports. This task consists of the resident field representative
keeping a diary, log book or report for those times on site, recording
hours on the job site; weather conditions; data relative to questions of
extras or deductions; list of visiting officials and representatives of
manufacturers, fabricators, suppliers and distributors; activities;
decisions, observations in general and specific observations in more
detail when necessary, as in the case of observing test procedures. As
part of this task weekly construction progress and inspection reports will
be prepared and submitted to the FAA.
19. Punch List. This task consists of conducting a review of the Project
near completion and preparing a list of items (Punch List) to be
completed or corrected.
20. Final Review. This task consists of performing a field observation of the
completed Project before a final application for payment is processed for
the Contractor.
21. Proiect Closeout. This task consists of assisting the Sponsor with
Project completion and final closeout documentation from the Contractor
for the FAA by providing a statement covering the following.
a. Sponsor Certification for Final Acceptance
b. Final Outlay Report — Standard Form SF-271
C. Final Project Cost Summary
d. Final Construction Report
1) Brief narrative of work accomplished as well as any
excluded items.
Page 4
2)
Summary of key milestone dates — Receipt of Bids, NTP,
Substantial Completion, Contract Date, Final Inspection,
Final Acceptance.
3)
Explanation of liquidated damages (if required).
4)
Statement of compliance with contract labor provisions
(payroll reviews, complaints, etc.) Reference AC
150/5100-6.
5)
Summary of final contract quantities.
6)
Explanation of underruns and overruns.
7)
Change Order Summary.
8)
Testing Report Summary including a copy of all
acceptance test results.
9)
Final Inspection Report including signature of consultant.
10)
Contractor's Final Statement of Completion — typically
submitted as the final payment request.
e. Summary of DBE Utilization
22. Record Drawings. This task consists of providing the Sponsor with a
copy of Record Drawings of the construction plans for the Project based
on the construction observation records of the review staff and
Contractor showing those changes made during construction considered
significant. Two copies of the Record Drawings in electronic and
reproducible format will be provided to the Sponsor. One electronic copy
would be for the FAA. Electronic drawings shall be in MicroStation V8
format. Task does not include updating of the Airport Layout Plans.
23. _Project Administration. This task consists of office administration and
coordination of the project. Interoffice meetings, general day-to-day
administrative responsibilities, and typing of interoffice memoranda and
minutes of meetings are included in this task.
L:\workWDMINWGREE\PROF\ICTaskOrder4Scope.doc
IV
V.
Rehabilitation of Runway 12-30
Iowa City Municipal Airport
Iowa City, Iowa
FAA Project No. 3-19-0047 - 19
CRS Services
Consultant Cost Summary
Direct Labor Cost
Category
Hours
Rate/Hour
Amount
Senior Professional
48
$79.00
$3,792.00
Project Professional
144
$64.00
$9,216.00
Staff Professional
146
$37.00
$5,402.00
CADD Operator
40
$25.00
$1,000.00
Senior Technician
710
$29.50
$20,945.00
Technician
394
$22.00
$8,668.00
Project Support
110
$19.50
$2,145.00 $51,168.00
1592
Payroll Burden and Overhead Provisional Costs
165.00% $84,427.20
Direct Project Expenses
Category
Units
Rate/Unit
Amount
Mileage
1800
0.550
990.00
Per Diem
0
30.00
0.00
Lodging
0
55.00
0.00
Copier
1200
0.06
72.00
Plan Copier
150
0.50
75.00
GPS
50
25.00
1,250.00
Geodimeter
60
12.50
750.00
Miscellaneous, Other
500.00
$3,637.00
Earth Tech Estimated Actual Costs
$139,232.20
Rounded
$139,200.00
Subcontract Expense
Terracon. - Testing Services
Estimated Actual Costs
Fixed Fee
Maximum Amount Payable
$7,500.00
$146,700.00
$20,300.00
$167,000.00
Rehabilitation of Runway 12-30
Iowa City Municipal Airport
Iowa City, Iowa
FAA Project No. 3-19-0047 -19
CRS Services
Staff Hour Estimate
Item
No.
Description
Senior
Prof
Project
Prof
Staff
Prof
CADD
Operator
Senior
TechniclarTechniciar
Project
Support
Totals
1
Assignment of Construction Manager
0
2
Assemble Construction Documents
4
8
8
20
3
Pre -Construction Conference
2
2
4
4
Construction Surveying
110
110
220
5
Shop Drawings and Submittals
12
16
1 12
40
6
Construction Observation Program
16
8
24
7
Construction Assistance
8
60
30
98
8
Pay Applications and Reimbursements
10
10
9
Labor and Payroll Reports
40
40
10
Testing of Materials
8
8
16
11
Site Visits
8
16
8
32
12
Change Orders
4
6
16
12
1 4
42
13
Pre -Paving Conference
8
4
4
16
14
Construction Observation
500
250
750
15
Non -Compliance Reporting
4
4
8
16
Contractor Modifications
4
4
8
17
Project Files
20
20
18
Daily Reports
60
30
90
19
Punch List
2
4
8
14
20
Final Review
2
4
8
14
21
Project Close-out
8
12
20
20
8
68
22
Record Drawings
4
8
20
32
23
Construction Administration
16
10
26
Total Construction Phase Services
48
144
146
40 1
710
394
110
1592
Prepared by: Michael Tharp, Operations Specialist, 1801 S. Riverside Dr, Iowa City IA 52246 319-350-5045
RESOLUTION NO.
RESOLUTION ACCEPTING THE WORK FOR THE SOUTH AIRFIELD
PLANNING STUDY
WHEREAS, the Airport Commission previously entered into supplemental agreement No. 4 with
Earth Tech (presently AECOM) for the south airfield planning study'; and
WHEREAS, the study has been approved by the FAA and is forwarded as complete by
AECOM.
NOW, THEREFORE, BE IT RESOLVED BY THE IOWA CITY AIRPORT COMMISSION THAT:
Said study is hereby accepted by the Iowa City Airport Commission.
Passed and approved this
CHAIRPERSON
ATTEST:
SECRETARY
day of
It was moved by and seconded by
adopted, and upon roll call there were:
Ayes
Nays
Approved by
City Attorney's Office
Absent
Farri s
Horan
Gardinier
Rettig
Staley
2009.
S - r 1--�S
the Resolution be
A UB� A va A
Michael Tharp
From: Edmonds, Terry D [terry-edmonds@uiowa.edu]
Sent: Thursday, May 14, 2009 9:17 PM
To: Michael Tharp
Subject: Iowa City Airport Hangar 66
Michael;
I am writing to seek approval to sub lease a portion of hangar 56 for a second aircraft. Mr. John Donovan has an
ultralight aircraft that will fit in the back part of the hangar by the garage door. Hangar 56 is large but odd
shaped and only a small airplane like an ultralight will fit as a second aircraft. This is a short term arrangement as
Mr. Donovan will be removing the aircraft in the fall. Mr. Donovan would reimburse me for the rent portion of
the hangar he uses. I believe this kind of arrangement is in alignment with airport policy of using hangar space as
efficiently as possible for aircraft use. Please present this request to the Airport Commission.
Terry Edmonds
4125 180th St NE
Solon IA 52333
PH 319-541-3437
5/18/2009
Airport Maintenance Activity and
Cost Report. Month of: April
Date
Maintenance Needed
Action Taken
Required Parts/Equipment
Cost
04/03/09
Hangar #60 light bulbs out
Bulbs Replaced
2 120w bulbs
INV
04/05/09
Rwy 12/30 Bulb out
Bulb Replaced
1 Runway bulb
INV
04/10/09
Rwy 12/30 Bulb out
Bulb Replaced
1 Runway bulb
INV
04/12/09
Fluids low in Mowers
Fluids Serviced
Gear, hyd, and motor oil
INV
04/13/09
Automated gates need serviced
Chains greased
Chain oil
INV
04/14/09
Automated gates need serviced
Gearboxes oiled
Gear oil
INV
04/16/09
Taxi way and parking area potholes
Asphalt patched
Asphalt
N/A
04/16/09
Skid Steer has a Flat
Tire placed on bead
Ratchet Strap, Air compressor
INV
04/08/09
Rwy 12/30 Bulb out
Bulb Replaced
1 Runway bulb
INV
04/20/09
0 turn mower, flat tire
Tire patched
1 Tire patch kit
INV
04/23/09
Rwy 12/30 Bulb out
Bulb Replaced
1 Runway bulb
INV
04/23/09
Mow Section 1 a
1a mowed — Toby
0 Turn
N/A
04/24/09
Mow Section 1 b
1 b Mowed — Kirk
0 Turn
N/A
04/24/09
Mow Section 3a
3a Mowed — Pat
Bat -wing
N/A
04/25/09
Mow Section 2
2 Mowed — Kirk
0 Turn
N/A
04/26/09
0 Turn Mower Maint. Due
Taken to streets
NIA
N/A
04/27/09
Skid Steer Maint. Due
Taken to streets
N/A
N/A
04/28/09
Mow Section 3b
3b Mowed — Ehren
Bat -wing
N/A
04/28/09
Mow Section 4a,b,c
4a,b,c Mowed — Ehren
Bat -wing
NIA
04/28/09
Mow Section 4d,e,f
4d,e,f Mowed — Kirk
Bat -wing
N/A
04/28/09
Case Tractor & Bat -wing Maint. Due
Taken to streets
N/A
N/A
04/28/09
Mow Section 1
1 Mowed — Pat
0 Turn
N/A
04/29/09
Mow Section 5a,b
5a,b Mowed — Kirk
Bat -wing
NIA
04/30/09
Mow Section 5c
5c Mowed — Ehren
Bat -wing
N/A
Amount to be reimbursed to Jet Air: $0.00
*Paid for or Purchased by Mike Tharp
INV — in inventory
Michael Tharp
From:
Mark W Vita [mvita@hertzcom]
Sent:
Thursday, May 14, 2009 10:03 AM
To:
Michael Tharp
Cc:
Jeffrey Homer
Subject:
RE: Hertz Lease at Iowa City Airport
Follow Up Flag:
Follow up
Flag Status:
Red
Michael:
In that event, please consider this e-mail an exercise of the option by Hertz. Thanks.
Mark W. Vita
Director, Properties & Concessions
The Hertz Corporation
2170 S. Mannheim Rd.
Des Plaines, I1. 60018
(847) 375-6511 -Phone
(847) 759-7466 -FAX
e-mail: mvita@hertz.com
"Michael Tharp"
<Michael-Tharp@iowa-city.org
05/14/2009 09:55 AM
Mark,
To
"Mark W Vita" <mvita@hertz.com>
cc
"Jeffrey Horner"
<JHorner@hertz.com>
Subject
RE: Hertz Lease at Iowa City
Airport
My apologies for the delayed response. The existing lease which expires July 31 2009,
contains an extension option for hertz.
If you choose to exercise the option the lease would extend to July 31, 2010. That notice
should be sent as soon as possible (lease says 90 days advanced notice).
Based on the language, it's my understanding that the terms would remain the same.
Mike
Michael Tharp, C.M.
operations Specialist
Iowa City Municipal Airport
1801 S. Riverside Dr
Iowa City, IA 52246
Phone: (319) 356 5045
1
Fax: (319) 351 1290
-----Original Message -----
From: Mark W Vita [mailto:mvita@hertz.com]
Sent: Friday, May 08, 2009 11:56 AM
To: Michael Tharp
Cc: Jeffrey Horner
Subject: Hertz Lease at Iowa City Airport
Michael:
Please provide me with the terms for a one year extension to our current lease. If Hertz
can stay on at the same rent as we currently pay I feel confident we will renew for
another year. Thanks.
Mark W. Vita
Director, Properties & Concessions
The Hertz Corporation
2170 S_ Mannheim Rd.
Des Plaines, I1. 60018
(847) 375-6511 -Phone
(847) 759-7466 -FAX
e-mail: mvita@hertz.com
This message (including attachments) may contain information that is privileged,
confidential or protected from disclosure. If you are not the intended recipient, you are
hereby notified that dissemination, disclosure, copying, distribution or use of this
message or any information contained in it is strictly prohibited. If you have received
this message in error, please immediately notify the sender by reply e-mail and delete
this message from your computer. Although we have taken steps to ensure that this e-mail
and attachments are free from any virus, we advise that in keeping with good computing
practice the recipient should ensure they are actually virus free.
---------------
This message (including attachments) may contain information that is privileged,
confidential or protected from disclosure. If you are not the intended recipient, you are
hereby notified that dissemination, disclosure, copying, distribution or use of this
message or any information contained in it is strictly'prohibited. If you have received
this message in error, please immediately notify the sender by reply e-mail and delete
this message from your computer. Although we have taken steps to ensure that this e-mail
and attachments are free from any virus, we advise that in keeping with good computing
practice the recipient should ensure they are actually virus free.
2
Monthly Expense Report - April '09
Check Requests During Month
Approved
Check Requests
4/6/2009 AECOM (Runway 12-30 Econ Stim)
4/62009 Jet Air (Maintenance/Cleaning Contract)
4/62009 Jet Air (Maintenance Supplies Reimbursement)
4/62009 AECOM (Hangar H Rehab)
4/6/2009 AECOM (North T-Hangar Taxilanes)
4/6/2009 AECOM (Runway 7.25 Phase 2 Design)
4/62009 AECOM (Runway 7-25 Rehab)
4/6/2009 AECOM (Runway 7-25 Reconstruct)
4/6/2009 AECOM (Runway 7-25 Paving and Lighting)
4/27/2009 LL Pelling (Asphalt)
4/27/2009 PIP (business cards)
42712009 Metro Pavers (Runway 725 Paving and Lighting Estimate # 8)
4/27/2009 AECOM (Runway 725 phase 2 design)
4/2712009 AECOME (Runway 12/30 Reconstruction
4/272009 AECOM (Runway 7.25 Paving and Lighting)
Capital Projects
Pending Expenses
Airport Operating Expenses
City CIP Fund Expenses
Total Expenses
Construction Contracts
South Economic Study -ALP Update
South T-Hangar Taxilane
Runway 7.25 Paving
United Hangar
Runway 7-26 Reconstruct and Alternate
North T-Hangar Ta)ilane Rehab
Total Pending Expenses
Airport Funds CIP Funds
$57,200.00
$5,000.00
$137.87
$956.62
$161.33
$104,580.00
$1,016.45
$1,817.58
$5,387.71
$129.65
$22.50
$70,835.28
$17,430.00
$57,200.00
$1,721.71
$5,137.87
$171,119.69 -
$176,257.56
Project Bid Amount Paid During Month Paid During FiscalYear Paid To Date %Paid
$15,000.00
$1,291.95
$13,726.07
91.5
$140,794.15
$98,935.64
$98,935.64
70.3
$1,347,586.13
$385,360.59
$1,341,228.72
99.5
$103,060.00
$94,562.69
$94,562.69
91.8
$1,449,848.70
$1,347,843.15
$1,347,843.15
93.0
$163,726.00
$153,843.43
$153,843.43
94.0
$0.00 $0.00
REVS: 05.18.09 12:37:00
Account
------------------------------------------
7600 Airport
CONTRIB & DONATIONS
362100 Contrib & Donations
Page: 1
Iowa City General Ledger System
FY 2009 Revenue Reporting
For the period 04.01.09 to 04.30.09
Estimated YTD Period
Revenue Revenue Revenue Remainder t
----------------------- ----------------------------------------------- ------
Total CONTRIB & DONATIONS
OTHER MISC REVENUE
369100 Reimb of Expenses
369900 Miscellaneous Other Income
Total OTHER RISC REVENUE
INTEREST REVENUES
381100 Interest on Investments
Total INTEREST REVENUES
RENTS
382100 Land Rental
382200 Building/Room Rental
Total RENTS
ROYALTIES & COMMISSIONS
384200 Vending Machine Comm
384900 Other Commissions
Total ROYALTIES & COMMISSIONS
TRANSFERS
TRANSFERS FROM GOVERNMENTAL ACTIVITIES
393120 General Levy
Total TRANSFERS FROM GOVERNMENTAL ACTIVITIES
Total TRANSFERS
Total Airport
ttt GRAND TOTAL tit
250.00
-250.00
------------ ------------
------------
250.00
------------
-250.00
------
28486.25
-28486.25
200.00
-200.00
------------------------
------------
28686.25
------------
-28686.25
------
1000.00
1477.21
308.33
-477.21
147.72
------------ ------------
1000.00
------------
1477.21
------------
308.33
-477.21
------
147.72
30700.00
32131.64
6955.93
-1431.64
104.66
226000.00
181234.33
16657.00
44765.67
80.19
------------------------
256700.00
------------
213365.97
---
23612.93
---------
43334.03
------
83.12
168.00
61.20
7.20
106.80
36.43
20000.00
15459.10
4540.90
77.30
------------------------
20168.00
------------
15520.30
------------
7.20
4647.70
------
76.96
130000.00
-----------------------
108333.30
10833.33
21666.70
83.33
130000.00
------------
------------
108333.30
------
10833.33
- -----
21666.70
------
83.33
------------
130000.00
------------
108333.30
------------
10833.33
21666.70
------
83.33
------------------------
407868.00
------------
------------
367633.03
------------
34761.79
40234.97
------
90.14
------------
407868.00
------------
367633.03
------------
34761.79
40234.97
------
90.14
E%PE: 05.18.09 12:36:29
Account
--------------
7600 Airport
AIRPORT
560100 Airport Operations
SALARIES & WAGES
REGULAR SALARIES & WAGES
411000 Perm Full Time
412000 Perm Part Time
413000 Temporary Employees
Total REGULAR SALARIES & WAGES
OTHER WAGES
414100 Overtime Wages
414300 Term -Vacation Pay
414400 Term -Sick Leave
414500 Longevity Pay
Total OTHER WAGES
Page: 1
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Appropriated Expenditures Expenditures Encumbrance Balance t Used
-------- ------------------------ ----------- ------------------------ ------
Total SALARIES & WAGES
EMPLOYEE BENEFITS
GROUP INSURANCE
421160 Health Insurance
421200 Dental Insurance
421300 Life Insurance
421400 Disability Insurance
421500 Unemployment Compensation
Total GROUP INSURANCE
SOCIAL SECURITY CONTRIBUTIONS
422100 FICA
Total SOCIAL SECURITY CONTRIBUTIONS
RETIREMENT CONTRIBUTIONS
423100 IPERS
Total RETIREMENT CONTRIBUTIONS
38611.00
17790.38
20820.62
46.09
22601.00
22997.03
2501.52
-394.03
101.74
10000.00
5101.89
4898.11
51.02
...................
71214.00
.............................................
45889.30
2501.52
25324.70
64.44
1000.00
473.28
526.72
47.33
1251.50
-1251.50
1720.57
-1720.57
1050.00
437.50
612.50
41.67
------------ ------------
2050.00
--
3882.85
--------- -----------
------------
-1832,85
------
189.41
73264.00
49772.15
2501.52
23491.95
67.94
7280.00
4360.56
285.62
2919.44
59.90
490.00
270.32
17.70
219.68
55.17
198.00
139.18
.85
58.82
70.29
460.00
132.45
14.10
327.55
28.79
832.00
-832.00
..................................................................
8428.00
5734.51
318.27
2693.49
68.04
5605.00
3110.56
183.63
1994.44
66.20
------------ ------------
5605.00
------------
3710.56
------------
183.63
------------
1894.44
------
66.20
4652.00
2762.93
158.84
1889.07
59.39
.................................................................
4652.00
2762.93
158.84
1889.07
59.39
C
EXPE: 05.18.09 12:36:29
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Account Appropriated Expenditures Expenditures
------------------------------------------------------ -----------------------------------
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
EMPLOYEE BENEFITS (CONTINUED)
OTHER EMPLOYER BENEFITS
424500 Monthly Cellular/PCS Allowance
Total OTHER EMPLOYER BENEFITS
Total EMPLOYEE BENEFITS
PROFESSIONAL & TECHNICAL SERVICES
PROFESSIONAL SRRVICRS
432020 Annual Audit
432060 Consultant Services
432070 Management Services
Total PROFESSIONAL SERVICES
DATA AND COMMUNICATION SERVICES
435056 Delivery Services
435060 Legal Publications
Total DATA AND COMMUNICATION SRRVICRS
TRAINING & EDUCATION
436030 Transportation
436050 Registration
436060 Lodging
436080 Meals
Total TRAINING & EDUCATION
INSURANCE
437010 Comp Liability Insurance
437020 Fire & Casualty Insurance
437030 Worker's Comp Insurance
437041 Bonding & Other Insurance
437042 Fidelity Bond
437200 Loss Reserve Payment
137.50
Page: 2
Encumbrance Balance t Used
------------------------ ------
137.50
-----------------------
------------ ------------
------------ ------------
137.50
------------
-137.50
------
18685.00
------------ ------------
12345.50 660.74
------------
6339.50
---- -
66.07
554.00
927.63
-373.63
167.44
5000.00
5000.00
9000.00
------------
4500.00
4500.00
50.00
------------
14554.00
------------------------
5427.63
------------
9126.37
------
37.29
36.98
-36.98
12.00
214.78 24.32
-202.78
1789.8
------------ ------------
12.00
------------ ------------
251.76 24.32
------------
-239.76
------
2098.0
900.00 900.00
400.00 400.00
500.00 500.00
150.00 150.00
------------------------------------------- ------------ ------
1950.00 1950.00
8578.00
5000.00
3578.00
58.29
16893.00
9640.03
7252.97
57.07
73.00
90.00
-17.00
123.29
928.00
875.00
53.00
94.29
5000.00
5000.00
100.00
E%PE: 05.18.09 12:36:29
Account
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Appropriated Expenditures Expenditures
----------------------------------------- -
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
PROFESSIONAL & TECHNICAL SERVICES (CONTINUED)
INSURANCE (CONTINUED)
Total INSURANCE
UTILITY SERVICES
438010 Stormwater Utility Charges
438030 Electricity
438070 Heating Fuel/Gas
438080 Sewer Utility Charge
438090 Water Utility Charge
438100 Refuse Collection Charges
438110 Local Phone Service
439120 Long Distance Service
438130 Wireless Phone Service
Total UTILITY SERVICES
Total PROFESSIONAL & TECHNICAL SERVICES
REPAIR & MAINTENANCE
BUILDING REPAIR & 1AINTENANCE SERVICES
442010 Other Building Repair & Maintena
442020 Structure Repair & Maintenance S
442030 Heating Equipment Repair & Maint
442040 Cooling Equipment Repair & Maint
442060 Electrical & Plumbing Repair & M
442070 Bldg Pest Control Services
Total BUILDING REPAIR & MAINTENANCE SERVICE
EQUIPMENT REPAIR & MAINTENANCE SERVICES
443050 Radio Equipment Repair & Mainten
443090 Other Equipment Repair & Mainten
-----------------------
31472.00 20605.03
Page: 3
Encumbrance Balance o Used
------------- -----
10866.97 65.47
7104.00
6619.60
591.96
484.40
93.19
15530.00
9531.84
78.57
5998.16
61.38
8680.00
7539.51
552.88
1140.49
86.86,
1475.00
1373.77
80.88
101.23
93.14
1321.00
1213.16
79.49
107.84
91.84
1200.00
965.00
99.00
235.00
80.42
264.00
676.92
-412.92
256.41
30.00
42.60
2.75
-12.60
142.00
-3.45
3.45
-----------------------
35604.00
-----------
27958.95
-•---------
1485.53
------------
7645,05
-
78.53
------------------------
83592.00
------------
54243.37
------------
1509.85
------------
29348.63
------
64.89
7500.00
7966.36
-466.36
106.22
4000.00
4460.27
-460.27
111.51
500.00
1657.80
-1157.80
331.56
1959.00
449.23
1509.77
22.93
500.00
264.59
235.41
52.92
431.00
339.50
33.95
91.50
78.77
-----------------------
14890.00
------------
15137.75
------------
33.95
------------
-247.75
------
101.66
1600.00
813.00 1299.38
------------ ------------
Total EQUIPMENT REPAIR & MAINTENANCE SERVIC 2413.00 1299.38
1600.00
-486.38 159.83
-- ------------------------ ------
1113.62 53.85
E%PE: 05.18.09 12:36:29 Page: 4
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Account Appropriated Expenditures Expenditures Encumbrance Balance % Used
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
REPAIR & MAINTENANCE (CONTINUED)
TECHNICAL SERVICES
445030 Nursery Service -Lawn and Plant C
445080 Snow and Ice Removal
445110 Testing Services
445140 Outside Printing
445230 Other Technical Services
Total TECHNICAL SERVICES
INTRA-DEPARTMENT SERVICES
446100 City Attorney Chargeback
446130 ITS-PC/Peripheral Support Charge
446140 ITS -Computer Replacement Chargeb
446160 ITS-Network/Internet Chargeback
446200 Photocopying Chargeback
446220 Phone Service Chargeback
446280 Telecom Move/Add/Change Chargeba
446300 Phone Equipment/Line Chargeback
446320 Mail Chargeback
446350 City Vehicle Replacement Chargeb
446360 City Vehicle Rental Chargeback
416370 Fuel Chargeback
446380 Vehicle Repair & Maintenance Cha
Total INTRA-DEPARTMBNT SERVICES
MISCELLANEOUS SERVICES & CHARGES
449055 Permitting Fees
449060 Dues & Memberships
449120 Equipment Rental
449140 Tools Rental
449360 Interest Expense
Total MISCELLANEOUS SERVICES & CHARGES
300.00
300.00
21500.00
4500.00
-21500.00
1900.00
1205.10
694.90
63.43
139.00
457.60
-318.60
329.21
5121.00
5121.00
------------ ------------
7460.00
------------
23162.70
------------
4500.00
------------
-15702.70
-----
310.49
4036.00
1768.96
2267.04
43.83
400.00
400.00
100.00
633.00
527.80
52.78
105.20
83.38
360.00
300.00
30.00
60.00
83.33
455.00
286.11
24.84
168.86
62.89
612.00
481.40
48.14
130.60
78.66
121.00
77.00
-121.00
913.00
775.00
77.50
138.00
84.88
706.00
483.61
74.79
222.39
68.50
14176.00
11631.28
1179.58
2544.72
82.05
143.00
143.00
-143.00
4861.00
3834.47
50.26
1026.53
78.88
3516.00
5979.74
1841.03
-2463.74
170.07
------------------------
30668.00
------------
26732.40
------------
3598.92
-----_----
3935.60
------
87.17
65.00
-65.00
525.00
625.00
-100.00
119.05
250.00
250.00
250.00
250.00
61294.00
38245.86
3824.59
23048.14
62.40
------------ ---
62319.00
---------------------
38935.86
------------
3824.59
------------
23383.14
------
62.48
EKPE: 05.18.09 12:36:29 Page: 5
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Account Appropriated Expenditures Expenditures Encumbrance Balance % Used
------------------------------------------------------------------------------------------------------------------- ------
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
REPAIR & MAINTENANCE (CONTINUED)
MISCELLANEOUS SERVICES & CHARGES (CONTINUED
-----------
Total REPAIR & MAINTENANCE
------------
117750.00
------------
105268.09
------------
11957.46
------------
12481.91
------
89.40
OTHER PURCHASED SERVICES (CHANGE TO OFFICE SU
GENERAL SUPPLIES
452010 Office Supplies
859.00
533.82
325.18
62.14
452030 Minor Office Equipment/Furniture
642.00
642.00
452040 Sanitation & Industrial Supplies
1821.00
1500.00
500.00
321.00
------------
82.37
------
------------
Total GENERAL SUPPLIES
------------
3322.00
------------
2033.82
------------
500.00
1288.18
61.22
BOOKS & PERIODICALS
454020 Subscriptions
1870.00
2036.00
-166.00
108.88
454040 Books, Magazines, Newpapers
------------
---------
------- -
--------
------
Total BOOKS & PERIODICALS
1870.00
2036.00
-166.00
108.88
COMPUTER & PRINTING SUPPLIES
455110 Software
91.00
-91.00
455120 Misc Computer Hardware
500.00
500.00
------
------------
Total COMPUTER & PRINTING SUPPLIES
------------
500.00
------------
91.00
------------
------------
409.00
18.20
------------
Total OTHER PURCHASED SERVICES (CHANGE TO OFF
------------
5692.00
------------
4160.82
------------
500.00
------------
1531.1E
------
73.10
OPERATING SUPPLIES
AGRICULTURE SUPPLIES
461040 Other Agriculture Chemicals
364.00
137.87
137.87
226.13
37.88
------------
Total AGRICULTURE SUPPLIES
------------
364.00
------------
137.87
------------
137.87
------------
226.13
------
37.88
CHEMICAL & LAB SUPPLIES
463200 Other Chemicals & Supplies
199.98
-199.98
------------
Total CHEMICAL & LAB SUPPLIES
------------
------------
199.98
------------
------------
-199.98
------
E%PE: 05.18.09 12:36:29
Account
---------------------------------------------
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
OPERATING SUPPLIES (CONTINUED)
FUELS & LUBRICANTS
465020 Gasoline
465030 Diesel Fuel
465060 Lubricants
Page: 6
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Appropriated Expenditures Expenditures Encumbrance Balance 8 Used
-------------------------------------------- ------------------------ ------
Total FUELS & LUBRICANTS
REPAIR & MAINTENANCE SUPPLIES
466020 Lumber/Hardware
466030 Paint Supplies
466040 Plumbing Supplies
466050 electrical Supplies
466060 Other Construction Supplies
466070 Other Maintenance Supplies
Total REPAIR & MAINTENANCE SUPPLIES
EQUIPMENT REPAIR & MAINTENANCE SUPPLIES
467020 Equipment Repair & Maintenance S
467160 Other Vehicle Repair & Maintenan
Total EQUIPMENT REPAIR & MAINTENANCE SUPPLI
SURFACING MATERIALS
468020 Concrete
468036 Asphalt
468050 Sand
Total SURFACING MATERIALS
OTHER SUPPLIES & EQUIPMENT
469010 Traffic Control Improvement Supp
469190 Minor Equipment
469200 Tools
469210 First Aid/Safety Supplies
469260 Fire Bat & Refills
133.52
-133.52
373.88
-373.88
101.00
------------
101.00
------------
101.00
------------------------
507.40
------------
-406.40
------
502.38
27.01
-27.01
23.00
23.00
6.00
6.00
349.00
19.53
329.47
5.60
838.00
838.00
589.00
------------ ------------
69.38
------------
519.62
11.78
1805.00
------------
115.92
-----------
1689.08
------
6.42
650.00
650.00
73.00
------------ ------------
73.00
723.00
------------------------
------------
723.00
------
153.00
153.00
600.00
600.00
54.00
------------------------
58.35
-4.35
108.06
807.00
------------------------
58.35
------------
748.65
------
7.23
106.00
330.00
-224.00
311.32
888.00
99.00
789.00
11.15
58.98
-58.99
57.00
57.00
111.00
78.50
32.50
70.72
EBPE: 05.18.09 12:36:29
Account
Page: 7
Iowa City General Ledger System
FY 2009 expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Appropriated Expenditures Expenditures Encumbrance Balance 4 Used
---------------------- - -------------- ------------------------ ------------ ------------ ------
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
OPERATING SUPPLIES (CONTINUED)
OTHER SUPPLIES 6 EQUIPI4ENT (CONTINUED)
469320 Miscellaneous Supplies
469360 Food and Beverages
Total OTHER SUPPLIES & EQUIPMENT
Total OPERATING SUPPLIES
IMPROVEMENTS OTHER THAN BUILDING
IMPROVEMENTS OTHER THAN BUILDING (GREATER
473010 Contracted Improvements
Total IMPROVEMENTS OTHER THAN BUILDING
OTHER FINANCIAL USES
490150 Operating Subsidy
490160 Misc Transfers Out
490190 Interfund Loan
Total OTHER FINANCIAL USES
Total Airport Operations
Total Airport
451.65 277.79
85.53
1162.00 1103.66 277.79
------------------------------- ------------
4962.00 2123.18 415.66
70390.00 8114.00
-------- ------------ ------------------------
70390.00 8114.00
8359.00
6965.80
28486.25
56426.00
19354.20
----------------------
64785.00
--
54806.25
------------ ------------
439120.00
290833.36
------------------------
439120.00
290833.36
-451.65
-85.53
58.34 94.98
2838.82 42.79
62276.00 11.53
-------- ------
62276.00 11.53
696.58
1393.20
83.33
-28486.25
1935.42
37071.80
34.30
-------- ------------
2632.00
------------
9978.75
------
84.60
-------- ------------
20177.23
------------
148286.64
------
66.23
-------- ------------
20177.23
------------
148286.64
------
66.23
E%PE: 05.18.09 12:36:29 Page: 8
Account
7600 Airport (CONTINUED)
AIRPORT (CONTINUED)
560100 Airport Operations (CONTINUED)
WEER FINANCIAL USES (CONTINUED)
Iowa City General Ledger System
FY 2009 Expense Reporting
For the period 04.01.09 to 04.30.09
YTD Period
Appropriated expenditures Expenditures Encumbrance
-------- ------- - ---- ------------ ------------ ------------
Balance 4 Used
------------ ------------ ----------- ---------------------- ------
GRAND TOTAL t*+ 439120.00 290833.36 20111.23 148286.64 66.23
TRID: 05.18.09 12:37:46
Iowa City General Ledger System
Revenues Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Page: 1
Trans Date
Trans Type
Report#
Source
Description Debit
Credit
-----------
7600 Airport
----------
------------
--------
-----------------------------------------------
-----------
560100 Airport Operations
381100 Interest on Investments
04.30.09
Allocation
090512112822
Apr interest allocation
308.33
Total Interest on Investments
------------
------------
308.33
382100 Land Rental
04.09.09
Payment
090409093333
00012589
1-6\TOYOTA OF IOWA CITY\PAYMENT
6717.00
04.27.09
Misc Pymt
090504171849
70-14\ARMED FORCES RESRRVE\AIRPORT
238.93
Total Land Rental
------------
------------
6955.93
382200 Building/Room
Rental
04.01.09
Payment
090401092008
00012628
1-8\BUTLER JOHN\APR 09\HANGAR #36
168.00
04.01.09
Payment
090401092008
00012628
1-8\BUTLER JOHN\APR 09\HANGAR #37
168.00
04.01.09
Payment
090401092008
00012632
1-12\SCHMEISBR RUSS\APR 09\HANGAR
204.00
04.01.09
Payment
090401092008
00012636
1-22\PATTSCRULL RICHARD\APR 09\HAN
229.00
04.01.09
Payment
090401092008
00012707
1-13\ADVANCED INFONBERING\PAYMENT
110.00
04.02.09
Payment
090402091920
00012630
1-18\N6226W INC\APR 09\HANGAR #49
173.00
04.02.09
Payment,
090402091920
00012658
1-11\ROOF KBITH\APR 09\HANGAR #32
512.00
04.06.09
Payment
090406095017
00012644
1-16\FARRIS GREG\APR 09\HANGAR #29
148.00
04.07.09
Payment
090407093106
00012599
1-2\FIELD HOWARD\APR 09\HANGAR #54
168.00
04.07.09
Payment
090407093106
00012624
1-34\YEAGBR DAN\APR 09\HANGAR 117
148.00
04.07.09
Payment
090407093106
00012624
1-34\YBAGER DAN\APR 09\HANGAR #26
148.00
04.07.09
Payment
090407093106
00012629
1-35\HARTWIG RANDY\APR 09\HANGAR #
168.00
04.07.09
Payment
090407093106
00012641
1-21\TEARSB DAVID\APR 09\HANGAR #4
168.00
04.07.09
Payment
090407093106
00012687
1-10\LUST GARY\APR 09\HANGAR 04
141.00
04,07.09
Payment
090407093106
00012687
1-10\LUST GARY\APR 09\HANGAR #21
148.00
04.00.09
Payment
090408091559
00012627
1.9\MASCARI RICK\APR 09\HANGAR #30
148.00
04.08.09
Payment
090408091559
00012662
1-4\OPERATOR PERFORMANCE LAB\APR 09
1330.00
04,08.09
Payment
090408091559
00012662
1-4\OPERATOR PERFORMANCE LAB\APR 09
168.00
04.09.09
Payment
090409093333
00012622
1-10\IOWA CITY FLYING CLUB\APR 09\H
168.00
04.09.09
Payment
090409093333
00012673
1-7\ALEXIS PARK INN 6 SUITES\APR 09
141.00
04.09.09
Payment
090409093333
00012678
1-3\WINGNUTS\APR 09\HANGAR #48
1008.00
04.10.09
Payment
090410095009
00012619
1.9\BULLERS JONATHAN\APR 09\HANGAR
141.00
04.10.09
Payment
090410095009
00012621
1.7\BULGARELLI ➢AVID\APR 09\HANGAR
148.00
TRID: 05.18.09 12:37:46
Iowa City General Ledger System
Revenues Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Trans Date Trans Type Report& Source Description
----------- -----------------------------------------------------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
382200 Building/Room Rental (CONTINUED)
04.10.09 Payment 090410095009
04.13.09 Payment 090413095444
04.14.09 Payment 090414093706
04.14.09 Payment 090414093706
04.14.09 Payment 090414093706
04.14.09 Payment 090414093706
04.14.09 Payment 090414093706
04.15.09 Payment 090415101710
04.15.09 Payment 090415101710
04.15.09 Payment 090415101710
04.15.09 Payment 090415101710
04,15.09 Payment 090115101710
04.15.09 Payment 090415101710
04.15.09 Payment 090415101710
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04.17.09 Payment 090417131622
04,17.09 Payment 090417152155
04.17.09 Payment 090417152155
04.17.09 Payment 090417152155
04.21.09 Payment 090421101252
04.22.09 Payment 090422110428
04.27.09 Payment 090427092817
04,28.09 Payment 090428102839
04.28.09 Payment 090429102939
04.28.09 Payment 090428102839
00012634 1-10\OCEENFELS TRANSFER\APR 09\HANG
00012626 1-10\BALL DAN\APR 09\HANGAR #27
00012606 1-10\RUYLE JOHN\APR 09\HANGAR #33
OD012617 1-5\RANBY CHARLES\APR 09\HANGAR 91
00012642 1-12\ZUBROD ROY\APR 09\HANGAR #20
00012674 1-21\VRANEK DOUGLAS\APR 09\HANGAR
00012704 1-3\ROAR BRIAN\APR 09\HANGAR #19
00012387 1-17\FULL JHRRY\MAR 09\HANGAR #45
00012623 1-9\HOLLY FORREST\APR 09\HANGAR 91
00012637 1-1\NB IA PHYS THERPY ASSOC\APR 09\
00012637 1-1\NE IA PHYS THERPY ASSOC\APR 09\
00012663 1-15\WIECHERT RONALD\APR 09\HANGAR
00012671 1.11\FLANAGAN JAMBS\APR 09\HANGAR
00012708 1-18\YELDER ROY\APR 09\HANGAR 818
00012597 89-1\MILLER RICHARD\APR 09\HANGAR
00012633 89-4\FISHBAUGH JUSTIN\APR 09\RANGA
00012638 89-5\ALLBNDER PATRICR\APR 09\HANGA
00012645 89-6\EDMONDS TERRY\APR 09\HANGAR @
00012654 89-10\SQUADRONS OP\APR 09\HANGAR 95
00012657 89-11\GURNBTT DON\APR 09\HANGAR $3
00012666 89-13\SINGLETARY ROBERT\APR 09\HAN
00012683 89.15\SWANSON NAOMI\APR 09\HANGAR
00012702 89-18\MEADS JAMBS N\APR 09\HANGAR
00012659 3.12\JBT AIR INC\APR 09\BUILDINGS D
00012665 2-11\STEARMAN\APR 09\BANGAR 147
00012677 3-12\JBT AIR\APR 09\HANGAR #60
00012667 1-25\SAPPHIRE VISTAS LLC\APR 09\HAN
00012640 1-29\CHALBLEY BEN\APB 09\HANGAR 11
00013088 2-10\POLASEI MICHABL\MAY 09\HANGAR
00013008 2-14\SCHMBISER RUSS\MAY 09\HANGAR
00013637 2.11\POWERS ROBBRT\MAY 09\HARGAR
00013045 2-6\DOWNES 6 ASSOCIATES\MAY 09\HANG
Page: 2
Debit Credit
204.00
148.00
358.00
141.00
148.00
141.00
148.00
204.00
148.00
198.DO
174.00
192.00
168.00
148.00
168.00
174.00
168.00
313.00
168.00
310.00
141.00
141.00
148.00
3926.00
168.00
174.00
148.00
148.00
148.00
204.00
141.00
168.00
TRID: 05.18.09 12:37:46
Iowa City General Ledger System
Revenues Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Page: 3
Trans Date
Trans Type
Report#
Source
Description Debit
-----------------------------------------------
Credit
------------
-----------
7600 Airport (CONTINUED)
----------
------------
--------
560100 Airport Operations
(CONTINUED)
382200 Building/Boom
Rental (CONTINUED)
04.28.09
Payment
090428102839
00013083
2-13\ADVANCED INFONEERING\PAYMBNT
110.00
04.28.09
Payment
090428110851
00012635
9-1\LACINA DAVB\APR 09\HANGAR #57
198.00
04.29.09
Payment
090429093312
00012985
2-10\BRUMLEY JAMBS\MAY 09\HANGAR #
148.00
04.29.09
Payment
090429093312
00013004
2-9\BUTLER JOHN\MAY 09\HANGAR #36
168.00
04.29.09
Payment
090429093312
00013004
2-9\BUTLER JOHN\MAY 09\HANGAR #37
168.00
04.29.09
Payment
090429093312
00013005
3-10\HARTNIG RANDY\MAY 09\HANGAR #
168.00
04.29.09
Payment
090429093312
00013006
2-7\N6226M INC\MAY 09\HANGAR #49
------------
168.00
------------
Total Building/Room
Rental
16657.00
384200 Vending Machine Comm
04.22.09
Misc Pymt
090422110433
1-39\AMERICAN BOTTLING\VENDING COMM
------------
7.20
------------
Total Vending Machine
Comm
7.20
393120 General Levy
04.30.09
Journal
090422104025
007528
Airport Prop Tx Supp\Apr Budgeted T
10833.33
Total General Levy 10833.33
------------ ------------
Total Airport Operations 34761.79
TRID: 05.18.09 12:37:46
Iowa City General Ledger System
Revenues Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Page: 4
Trans Date Trans Type Report# Source Description Debit Credit
----------- ---------------------- ------------------------------------------------------- ---------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
Total Airport 34761.79
TRID: 05.18.09 12:37:46
Trans Date Trans Type
-
---------- ----------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
*** GRAND TOTAL "t
Page: 5
Iowa City General Ledger System
Revenues Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Report# Source Description Debit Credit
--------- -------- ----------------------------------- ---------------------
34761.79
------------------------
------------------------
TRID: 05.18.09 12:37:36
Page: 1
Iowa City
General Ledger System
Expenditures
Detail
FY
2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Trans Date Trans Type
Report#
Source Description
Debit Credit
---------------------
7600 Airport
------------
----------------- -------------------------- ------------
------------
560100 Airport Operations
412000 Perm Part Time
04.10.09 Old Sys
090409010011
490303\CIC PAYROLL RECAP\PAYROLL 10
1359.72
04.24.09 Old Sys
090422010008
490535\CIC PAYROLL RECAP\PAYROLL 24
1141.80
Total Perm Part Time
-----------
- ------------
2501.52
421100 Health Insurance
04.08.09 Journal
090422104025
007526 APR HEALTH INSURANCE\CIC HEALTH INS
285.62
Total Health Insurance
------------
------------
285.62
421200 Dental Insurance
04.08.09 Journal
090422104025
007525 APR DENTAL INSURANCE\CIC DENTAL INS
17.70
Total Dental Insurance
------------
------------
17.70
421300 Life Insurance
04.01.09 Journal
090422104025
007527 APR LIFE INSURANCE\CIC LIFE INSURAN
.85
Total Life Insurance
------------
------------
.85
421400 Disability Insurance
04.08.09 New Vouch
090409030154
06721762 Check:643253\NADISON NATIONAL LIFE
14.10
Total Disability Insurance
------------
------------
14.10
422100 FICA
04.10.09 Old Sys
090408010011
4100599\FICA\CITY CONTRIBUTION
100.15
04.24.09 Old Sys
090422010008
4240599\FICA\CITY CONTRIBUTION
83.48
Total FICA
------------
------------
183.63
423100 IPERS
04.10.09 Old Sys
090408010011
4103599\IPERS\CITY CONTRIBUTION
86.34
04.24.09 Old Sys
090422010008
4243599\IPERS\CITY CONTRIBUTION
72.50
Total IPERS
------------
------------
158.84
TRID: 05.18.09 12:37:36 Page: 2
Iowa City General Ledger System
Expenditures Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Trans Date Trans Type Report# Source Description Debit Credit
----------- ---------- ------------ ------------------------------------------- ------------ ------------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
435060 Legal Publications
04.22.09 New Vouch 090423030128 06722678 Check:643767\IOWA CITY PRESS CITIZB 24.32
------------ ------------
Total Legal Publications 24.32
138010 Stormwater Utility Charges
04.15.09 Journal 090422104025 007524 057-095-03\STORMWTR\4.15.09 Bill Da 591.96
------------ ------------
Total Stormwater Utility Charges 591.96
439030 Electricity
04.22.09 New Vouch 090423030128 06722691 Check:643793\MIDAMBRICAN RNBRGY%R 78.57
Total Electricity
438070 Heating Fuel/Gas
04.22.09 New Vouch
04.22.09 New Vouch
04.22.09 New Vouch
Total Heating Fuel/Gas
439080 Sewer Utility Charge
04,15.09 Journal
04.15.09 Journal
04.15.09 Journal
04.15.09 Journal
Total Sewer Utility Charge
438090 Water Utility Charge
04.15.09 Journal
04.15.09 Journal
04.15.09 Journal
04.15.09 Journal
04.15.09 Journal
------------
78.57
090423030128 06722692 Check:643793\MIDAMBRICAN ENERGY\GAS 10.00
090423030128 06722700 Check:643793\MIDAMBRICAN ENERGY\GAS 98.24
090423030128 06722742 Check:643794\MIDAMBRICAN ENERGY\GAS 444.64
552.88
090422104025
007524
057.120.00\SEWER\4.15.09
Bill
Date
24.51
090422101025
007524
057-118-03\SBWBR\4.15.09
Bill
Date
16.13
090422104025
007524
057-117-00\SBWBR\4.15.09
Bill
Date
32.09
090422104025
007524
057-115.00\SBWBR\4.15.09
Bill
Date
8.15
------------ ------------
80.88
090422104025
007524
057-120-00\WATBR\4.15.09
Bill
Date
18.67
090422104025
007524
057-118-03\WATBR\4.15.09
Bill
Date
12.39
090422104025
007524
057-117.00\WATER\4.15.09
Bill
Date
24.35
090422104025
007524
057-115-00\WATBR\4.15.09
Bill
Date
16.47
090422104025
007524
057-095-03\WATBR\4.15.09
Bill
Date
7.61
Total Water Utility Charge 79.49
TRID: 05.18.09 12:37:36
Trans Date Trans Type
Iowa City General Ledger System
Expenditures Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Report@ Source Description
Page: 3
Debit Credit
7600 Airport (CONTINUED(
560100 Airport Operations (CONTINUED)
438100 Refuse Collection Charges
04.14.09 New Vouch 090415030033 06722051 Check:643426\ALLIED WASTE SERVICES\ 74.00
04.14.09 New Vouch 090415030033 06722051 Check:643426\ALLIED WASTE SERVICES\ 25.00
Total Refuse Collection Charges
438120 Long Distance Service
04.01.09 Ph Lon Dst 090501113823 00004019 APR LONG DIST CHGBH
Total Long Distance Service
442070 Bldg Pest Control Services
D4.08.09 New Vouch 090409030154 06721799 Check:643227\BANEEYE PEST CONTROL I
Total Bldg Peat Control Services
445080 Snow and Ice Removal
04.13.09 New Vouch 090414030008 06721940 Check:643497\JRT AIR INC IOW\SNOW R
Total Snow and Ice Removal
446140 ITS -Computer Replacement Chargeback
04.01.09 IT Repl 090406135513 00004025 APR ITS RBPL CHGBCE
Total ITS -Computer Replacement Chargeback
446160 ITS-Network/Internet Chargeback
04.01.09 IT Int/Nwk 090402160547 00004031 APR ITS NETW/INTRNET
99.00
2.75
-------------------
2.75
33.95
-------------------
33.95
4500.00
------------ -------
4500.00
52.78
------------ -------
52.78
30.00
----------------- ------
Total ITS-Network/Internet Chargeback 30.00
446200 Photocopying Chargeback
04.30.09 Journal 090505172207 007587 MAR PHOTOCOPY\CIC CENTRAL SERVICE C 24.84
------------ ------------
Total Photocopying Chargeback 24.84
446220 Phone Service Chargeback
04.30.09 Qwest Chrg 090501104348 00005032 Apr Qwest Charges 48.14
Total Phone Service Chargeback 48.14
TRID: 05.18.09 12:37:37
Trans Date Trans Type
----------- ----------
Page: 4
Iowa City General Ledger System
Expenditures Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Report# Source Description Debit Credit
--------- ------------------------------------------------------- ---------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
446280 Telecom Move/Add/Change Chargeback
04.30.09 IT Ann Sup 090504090205 00004024 APR PHONE SERV
Total Telecom Move/Add/Change Chargeback
446300 Phone Equipment/Line Chargeback
04.01.09 Ph Equipmt 090501113823 00004018 APR PHON EQUIP CHGBB
Total Phone Rquipment/Line Chargeback
446320 Mail Chargeback
04.01.09 Mail 090402105154 00400048 MAR POSTAL CHARGES
Total Mail Chargeback
446350 City Vehicle Replacement Chargeback
04.30.09 EQ Repl 090504101048 00004006 APR REPLACEMENT COST
Total City Vehicle Replacement Chargeback
446360 City Vehicle Rental Chargeback
04.30.09 EQ Oper 090504101048 00004007 APR OPERATION COST
Total City Vehicle Rental Chargeback
446370 Fuel Chargeback
04.30.09 EQ Div 090504101048 00004008 APR DIVISION FUEL
Total Fuel Chargeback
446380 Vehicle Repair & Maintenance Chargeback
04.30.09 EQ Div 090504101048 00004008 APR DIVISION SERVICE
Total Vehicle Repair & Maintenance Chargeback
449360 Interest Expense
04.30.09 Journal 090422104025 007532 Corp Hangar Loan Int\Apr Interfund
04,30.09 Journal 090422104025 007532 Airprt SR Hangar Int\Apr Interfund
04.30.09 Journal 090422104025 007532 Airprt SW Hangar-Int\Apr Interfund
143.00
------------ ------------
143.00
50.26
------------ ------------
50.26
1841.03
------------ ------------
1841.03
1904.56
991.02
929.01
TRID: 05.18.09 12:37:37
Iowa City General Ledger System
Expenditures Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Trans Date Trans Type Report# Source Description
----------- ---------- ------------ -------- -----------------------
7600 Airport (CONTINUED(
560100 Airport Operations (CONTINUED(
449360 Interest Expense (CONTINUED(
Total Interest Expense
452040 Sanitation & Industrial Supplies
04.13.09 New Vouch 090414030008 06721939 Check:643497\JET AIR INC IOW\CLEANI
Total Sanitation & Industrial Supplies
461040 Other Agriculture Chemicals
04.13.09 New Vouch 090414030008 06721941 Check:643497\JET AIR INC IOW\AIRPOR
Total Other Agriculture Chemicals
469320 Miscellaneous Supplies
04.21.09 P-Card 090506141731 15100411 MENARDS IOWA CITY\MICHAEL THARP
04.21.09 P-Card 090506141731 15100412 MHNARDS IOWA CITY\MICHAEL THARP
04.21.09 P-Card 090506141731 15100413 MENARDS IOWA CITY\MICHAEL THARP
04.21.09 P-Card 090506141731 15100414 MENARDS IOWA CITY\MICHARL THARP
04.21.09 P•Card 090506141731 15100415 LOWBS #01688+\MICHARL THARP
Total Miscellaneous Supplies
490150 Operating Subsidy
04.30.09 Journal
Total Operating Subsidy
490190 Interfund Loan
04.30.09 Journal
04.30.09 Journal
04.30.09 Journal
Total Interfund Loan
Total Airport Operations
090422104025 007528 Econ Dev Coord 10%\Apr Budgeted Tra
090422104025 007532 Corp Hangar Loan Prn\Apr Interfund
090422104025 007532 Airprt SH Hangar Prn\Apr Interfund
090422104025 007532 Airprt SW Hangar-Prn\Apr Interfund
Page: 5
Debit Credit
------------ -------
------------ ------------
3824.59
------------
3824.59
500.00
------------------------
500.00
137.87
------------------------
137.87
149.35
74.28
19.08
21.70
13.38
------------------------
277.79
696.58
--------------------
696.58
1095.44
338.98
501.00
-------- ------------
1935.42
-------- ------------
20177.23
TRID: 05.18.09 12:37:37
Iowa City General Ledger System
Expenditures Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Page: 6
Trans Date Trans Type Report# Source Description Debit Credit
---------------------------------------------------------------------------- ------------ ---------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
490190 Interfund Loan (CONTINUED)
------------ ------------
Total Airport 20177.23
TRID: 05.18.09 12:37:37
Iowa City General Ledger System
-Expenditures Detail
FY 2009 Detail Reporting
For the period 04.01.09 to 04.30.09
Trans Date Trans Type Report# Source
----------- ---------- ------------ -------
7600 Airport (CONTINUED)
560100 Airport Operations (CONTINUED)
490190 Interfund Loan (CONTINUED)
"' GRAND TOTAL ttt
Page: 7
Description Debit Credit
--------------------------- ------------ ------------
20177.23
------------------------
------------------------