NOTICE OF PUBLIC HEARING
NOTICE OF PUBLIC HEARING ON PROJECT MANUAL AND
ESTIMATED COST FOR THE BENTON STREET
REHABILITATION PROJECT IN THE CITY OF IOWA CITY,
IOWA
TO ALL TAXPAYERS OF THE CITY OF IOWA CITY, IOWA, AND
TO OTHER INTERESTED PERSONS:
Public notice is hereby given that the City Council of the City
of Iowa City, Iowa, will conduct a public hearing on the Project
Manual, including the plans, specifications, contract, and
estimated cost for the construction of the Benton Street
Rehabilitation Project in said city at 6:00 p.m. on the 19th day of
April, 2022, said meeting to be held in the Emma J. Harvat Hall in
City Hall, 410 E. Washington Street in said city, or if said meeting
is cancelled, at the next meeting of the City Council thereafter as
posted by the City Clerk.
This project includes a crack and seat of the existing pavement
with a Hot Mix Asphalt (HMA) overlay, painting of on -street bike
lanes, ADA sidewalk improvements, and traffic and pedestrian
signal improvements at the Benton and Sunset intersection. This
project also includes water main and storm sewer improvements
and is located in the City of Iowa City from Greenwood Drive to
Mormon Trek Boulevard.
Said Plans and estimated cost are now on file in the office of
the City Clerk in the City Hall in Iowa City, Iowa, and may be
inspected by any interested persons.
Any interested persons may appear at said meeting of the City
Council for the purpose of making objections to and comments
concerning said Plans or the cost of making said improvement.
This notice is given by order of the City Council of the City
of Iowa City, Iowa and as provided by law.
Kellie K. Fruehling, City Clerk
Benton Street Rehabilitation Project 0110 - Page 1 of 1
Benton Street Rehabilitation
Project
Iowa City City Council Meeting
April 19, 2022
� r
1
--‘12"mmc311
CITY OF IOWA CITY
UNESCO CITY OF LITERATURE
Background
• On 01/19/22, one bid exceeding the Engineer's Estimate of Probably
Cost by more than 40%. Re -bid on June 21, 2022.
• Project corridor— Greenwood Dr to Mormon Trek Blvd
• Diamond grinding project completed within this section in 2007
• Pavement in poor condition with increasing joint deterioration
• IVPOJC programmed $1.3 Million in STBG funding in the FY21 — FY24 TIP
for rehabilitation
vit
11PF ' s�
4.
V.
11011111J1N111
Project Overview
• Project partially funded by the Iowa DOT
• This project includes:
• Crack and Seat of the existing pavement with a 3" asphalt overlay
• Side street intersection reconstruction and ADA sidewalk improvements
• Pavement widening and signal improvements at the Sunset intersection
• Water main and storm sewer improvements
• New 5'-0" bike lanes
• Changes included for the re -bid
• Items clarified by addendum have been added.
• Added 2 critical closures for sewer work
• Schedule provides additional flexibility
• Clarified water separation from HP Gas
ROW (VARIES)
EXISTING PAVEMENT ]]A' B43
16.5. f 159
225
5.5' SINE
14A. CRACK AND SEAT WIDTN _ 25
14A CRACK AND SEAT WIDTH
LANE 11.5 THRU LANE 11A'THRU LANE 5.5. BIKE LANE
I
MATCH E% -__ MATCH EXMMUMW
7
Estimated Construction Cost
• $4,200,000
*Revised by McClure after rejection of the first bid & based on current Awarded Contract
Prices as reported by the Iowa DOT.
Project Timeline
• Hold Public Hearing / Approve Plans and Specifications —April 19, 2022
• Iowa DOT Bid Letting —June 21, 2022
• Award Date—July 5, 2022
• Construction Start — Fall 2022 / Spring 2023
• Final Completion — Fall 2023
Questions?
FILED
APR 0 2022
City Clerk
Iowa City, Iowa
NOTICE OF PUBLIC HEARING
NOTICE OF PUBLIC HEARING ON PROJECT MANUAL
AND ESTIMATED COST FOR THE NORTH
WESTMINSTER STORM SEWER UPGRADES PROJECT
IN THE CITY OF IOWA CITY, IOWA
TO ALL TAXPAYERS OF THE CITY OF IOWA CITY,
IOWA, AND TO OTHER INTERESTED PERSONS:
Public notice is hereby given that the City Council of the
City of Iowa City, Iowa, will conduct a public hearing on the
Project Manual, including the plans, specifications, contract,
and estimated cost for the construction of the North
Westminster Storm Sewer Upgrades in said city at 6:00 p.m.
on the 19th day of April, 2022, said meeting to be held in the
Emma J. Harvat Hall in the City Hall, 410 East Washington
Street in said city, or if said meeting is cancelled, at the next
meeting of the City Council thereafter as posted by the City
Clerk.
This Project will involve the installation of approximately
1,300 linear feet of storm sewer pipe and associated
structures, approximately 4,200 square yards of concrete
pavement replacement, approximately 1,500 square yards
of sidewalk replacement and associated landscape
restoration and is located at, and adjacent to, the
intersection of E Washington Street and North Westminster
Street in Iowa City, Iowa 52245
Said Project Manual and estimated cost are now on file
in the office of the City Clerk in the City Hall in Iowa City,
Iowa, and may be inspected by any interested persons.
Any interested persons may appear at said meeting of
the City Council for the purpose of making objections to and
comments concerning said Project Manual or the cost of
making said improvement.
This notice is given by order of the City Council of
the City of Iowa City, Iowa and as provided by law.
Kellie K. Fruehling, City Clerk
1
Public Hearing
North Westminster Storm Sewer
Improvements Project
Iowa City
City Council
Regular Formal Agenda
April 19th, 2022
•
PROJECT LOCATION
1
218
'.94
z
Lucas
Twp",
Sycamore Si SE
1 Scott I NI
rIQUX AveSE
OGN�s�� PSE
R
ARBOR HILL CIRCLE
•
z
J w
SHRADER RD
WESTMINSTER ST
•
•
}
r
HASTINGS AVE
PROJECT LOCATION
LEMME
ELEMENTARY
WASHINGTON ST
j - s
DARTMOUTH ST
•
:1
SCOTT BLVD
lir
'- l -,
ftalia
Jr
Timeline
• 2015 Reports of Flooding During Intense Rain Events
• 2017 Drainage Study Completed by Shive-Hattery
• 2019 Project funded in 5 -year Capital Improvements Program
• 2021 Design, Public Meetings and Easement Acquisitions
• 2022 Bidding and Construction
.11
WASHINGTON ST.
LEGEND
• DEFICIENT STRUCTURE • 1 YEAR STORM
UNDERSIZED PIPE - 1 YEAR STORM
• DEFICIENT STRUCTURE • 5 YEAR STORM
UNDERSIZED PIPE - 5 YEAR STORM
Location
Deficient
Storm Event
Impact During Deficient Storm Event
Westminster Street
between Bowling Green PI.
and Washington St.
1 -year
The trunk sewer is undersized and structures along
Westminster flood or surcharge. There is no overland
flow route along the street, so water tends to pond in the
street and can overflow into the property of 15
Westminster. Some of the excess water may also flood
into Washington Street and contribute to issues there.
Washington Street between
Westminster St. and
Shrader Rd.
1 -year
Pipes are undersized and structures along Washington
are flooded or surcharging. The low spot in the street
ponds water and causes issues for vehicles.
Westminster Street
between Hastings Ave. and
Washington St.
1 -year
Intakes are undersized or spaced too far apart south of
Hastings Avenue. There is excessive gutter flow within
Westminster Street south of Hastings.
Washington Street between
Westminster St. and
Creighton St.
1 -year
Intakes are undersized or spaced too far apart for this
stretch and pipes are undersized. There is excessive
gutter flow within the street for this stretch which also
contributes to issues at the low spot farther south.
, - -
t
. ; !WESTMINSTER ST. TRUNK
SEWER UPGRADE
•
. I / Ili • -
• .
L
\ ,
, \
ND INTAKE UPGRADES
ASHINGTON ST. PIPE
L,,•: -;;:t
12147114.11.14811.th1 i48
mazizEmm
INEV4 MANHOLE
L I
--
NEW CURB
INTAKES
NEW BEEHIV
INTAKE
/
71.7E%
WESTMINSTER ST.
INTAKES
UPSIZE 36. TO 481
NEW CURB INTAKES'
NEW URB
INTAKES
fl
1 ii -ii•
1 ! - 1, - q,'"'L'
I
pi
I ' — I I — -'- 4
1 ,
.--'-r-:=_==-
1 i :..:
\ i
048TEUI1IE:311 11 II 214115111010:111
A I " 't4.
...
0 7_,
,NVIallIgitIMY fX.I*L
ILI L
,I--1 ,_, i
EW MANHOLE I — I-, r — — —' r — 1 I—
II tiTJC *-11 in -1 I --II L T '' L -1-1 1 I 7.
' L — —
1 L
1--
,
REGRADE
WESTMINSTER ST.
UPSIZE 36" TO 48
li48K1macE3-10"
=mum=
zrasimuu
Vi83n5Uft.
—
I /
I --
r
_ ,
UPSIZE 18" TO 361
Bidding and Construction Timeline
• $1,350,000 Estimated Cost of Construction
• May 10th Bids Due
• May 17th Award Contract
• June 2022 Begin Construction
• May 2023 Substantial Completion
13.
0110
NOTICE OF PUBLIC HEARING
NOTICE OF PUBLIC HEARING ON PROJECT MANUAL
AND ESTIMATED COST FOR THE WETHERBY PARK
SIDEWALK AND ENTRANCE PROJECT IN THE CITY OF
IOWA CITY, IOWA
TO ALL TAXPAYERS OF THE CITY OF IOWA CITY,
IOWA, AND TO OTHER INTERESTED PERSONS:
Public notice is hereby given that the City Council of the
City of Iowa City, Iowa, will conduct a public hearing on the
Project Manual, including the plans, specifications, contract,
and estimated cost for the construction of the Wetherby
Park Sidewalk And Entrance in said city at 6:00 p.m. on the
19th day of April, 2022, said meeting to be held in the Emma
J. Harvat Hall in the City Hall, 410 East Washington Street
in said city, or if said meeting is cancelled, at the next
meeting of the City Council thereafter as posted by the City
Clerk.
This project includes removal and construction of
concrete sidewalks and reconstruction of the driveway
entrance at Wetherby Park in Iowa City, IA.
Said Project Manual and estimated cost are now on file
in the office of the City Clerk in the City Hall in Iowa City,
Iowa, and may be inspected by any interested persons.
Any interested persons may appear at said meeting of
the City Council for the purpose of making objections to and
comments concerning said Project Manual or the cost of
making said improvement.
This notice is given by order of the City Council of
the City of Iowa City, Iowa and as provided by law.
Kellie K. Fruehling, City Clerk
Wetherby Park Sidewalk And Entrance Project 0110 — Page 1 of 1
Taylor
Drive
Wetherby Park
Sidewalk and
Entrance Project
• ADA Curb Ramps
• Sidewalk to connect to Trail
• Entrance Reconstruction
• Trail Connection to Community Garden
• West Trail Connection
• Asphalt Patch
Wetherby Park Sidewalk and Entrance Project
• Cost Estimate - $93,000
• Public Hearing — April 19th
• Bid Letting — May 10th
• Accept Bid — May 17th
• Construction Start —June 2022
• Construction Completion — Fall 2022
Notice o f Public Hearing
Notice is hereby given that a public hearing will
be held at which the Council will consider:
Ordinance amending Title 3, Entitled
"Finances, Taxation and Fees," Chapter 4,
entitled "Schedule of Fees, Rates, Charges,
Bonds, Fines and Penalties," of the City Code
to increase solid waste disposal charges and
fees.
Copies of the proposed ordinance are on file
for public examination in the office of the City
Clerk, City Hall, 410 E. Washington St., Iowa
City, Iowa. Copies are available by telephoning
the City Clerk at 319/356-5043 or emailing
kellie-fruehlinq aniowa-citv.orq.
The public hearing will be held at 6:00 p.m. on
April 19, 2022, in the Emma J. Harvat Hall, City
Hall, Iowa City. Persons wishing to make their
views known for Council consideration are
encouraged to participate.
Kellie K. Fruehling, City Clerk
E
.1?1 APR - I PH 3:0f
Prepared by: Jacklyn Fleagle. Budget & Compliance Officer, 410 E. Washington Street, Iowa City, IA 52240: 319-
356-5063
Ordinance No.
Ordinance Amending Title 3, Entitled "City Finances, Taxation And Fees," Chapter 4, Entitled "Schedule
Of Fees, Rates, Charges, Bonds, Fines, And Penalties," Section 3-4-5, Entitled "Solid Waste Disposal"
Whereas, pursuant to Chapter 384, Code of Iowa (2013), the City of Iowa City is authorized to establish and
provide for the collection of rates to pay for the City's utility systems, including the City's solid waste disposal
services at the municipal landfill; and
Whereas, the City's financial policies dictate that the Refuse fund shall be self-supporting; and
Whereas, the City's current solid waste disposal rate structure does not provide sufficient revenue to fund the
necessary operations; and
Whereas, the Iowa City Council intends to provide a solid waste disposal rate and fee structure that makes
the City's refuse utilizes self-sustaining; and
Whereas, the Iowa City City Council to increase residential solid waste collection fees for yard waste
collection by $1.50 per dwelling unit, per month, to increase additional yard waste carts over 1, per month by
$1.50 each, to increase curbside household refuse for solid waste disposal by $1.00 per dwelling unit, per
month, to increase the additional refuse carts over 1, per month by $1.00 each. and to increase curbside
recycling by $.50 per dwelling unit. per month on July 1, 2022, to adequately finance the municipal refuse
operational costs;
Now, therefore. be it ordained by the City Council of the City of Iowa City, Iowa:
Section I. Amendment. Title 3, entitled "City Finances. Taxation, and Fees," Chapter 4, entitled "Schedule of
Fees. Rates, Charges, Bonds, Fines. and Penalties," Section 3-4-5, entitled "Solid Waste Disposal." of the
Iowa City Code is hereby amended by deleting it in its entirety and replacing it as follows:
3-4-5: Solid Waste Disposal:
Description Of Fee, Charge, Bond, Fine Or Penalty
Yard waste collection fees:
Per dwelling unit, per month
$3.50
Charge
tow income discount 75 percent of monthly charge
LL1 'Untreated wood waste
;Additional yard waste carts over 1, per month
Collection of Targe items fees:
Free
$3.50
Appliance collection, per item collected $20.00
Bulky solid waste
$12.50 per stop and 1 item; $6.00 per
additional items
Tire collection $3.75 per tire; $7.50 tire and rim
Residential solid waste collection fees:
Curbside household refuse:
mei
Ordinance No. _ _
Pacie 2
Description Of Fee, Charge, Bond, Fine Or Penalty
Per dwelling unit, per month
Low income discount
Per sticker for each additional bag beyond each unit's
monthly allotment
Additional refuse carts over 1, per month
Per 2 rooming units, per month (in addition to the dwelling
unit fees)
Electronic waste
Curbside recycling:
r
r
Iowa City community compost
Wood chip mulch
$13.00
Charge
75 percent of monthly charge
$ 2.50 each
$13.00 each
$15.90
TVs or monitors $21.50 per item
Per dwelling unit, per month
Low income discount
1—
• Deposit and delinquency fee combined for City water and/or
sanitary sewer and/or solid waste collection accounts:
Residential owner account, per combined residential service
for City water and/or sanitary sewer and/or solid waste
collection service
Residential tenant account, per combined residential service
for City water and/or sanitary sewer and/or solid waste
collection service
5 percent delinquency charge on current billed portion of the
outstanding amount on combined water and/or sanitary sewer
,and/or solid waste account that is not paid within 22 days of
.Milling date
Delinquency deposit for combined water and/or sanitary sewer
arEl or solid waste collection service
Special wastes disposal fees:
I Disposal of special wastes (except for asbestos containing
material and contaminated soils)
Minimum fee
Asbestos containing material (ACM):
Nonfriable ACM, from Iowa City premises subject to a
Property Tax and City owned property
ILFNonfriable ACM, from other locations
Friable ACM, from Iowa City premises subject to a
Property Tax and City owned property
S6.50
75 percent of monthly charge
$20.00 per ton, $2.00 minimum
No charge
$0.00
$120.00
5 percent current billed portion. Can be
waived once every 12 months
An amount equal to an average 2 -month
billing for the delinquent account. Can be
waived if the account holder enrolls in
SurePay
2 times the landfill use fees in this section
2 times the landfill use fee for 1 ton
$100.00/ton
$105.00/ton
$100.00/cubic yard
Ordinance No.
Page 3
Description Of Fee, Charge, Bond, Fine Or Penalty Charge
Friable ACM, from other locations $105.00/cubic yard
Minimum fee for any regulated ACM $100.00
Contaminated soil: $50.00/ton
Minimum fee for contaminated soil $150.00
Disposal of large items fees (see also Collection of large items
fees above):
Appliance disposal fees:
Commercial per item disposed $1.00/cubic foot
Residential per item disposed $12.50 (at landfill scale house)
Tire disposal fee:
Per pound $0.15
Subject to minimum fee $3.00
Untreated wood waste and yard waste: $24.00/ton
Minimum $2.00
Landfill use fees:
Arriving at the landfill with an unsecured or uncovered load:
First instance in trailing 12 months Warning
Second.or subsequent instances in trailing 12 months $50.00
Electronic waste $3.00 per item; TVs or monitors $15.00 per
c _ item
Solid waste from Iowa City premises subject to a Property Tax
pnd City owned property:
Total landfill fee per ton (includes State fee per ton) $45.00
All other solid waste:
Total landfill fee per ton (includes State fee per ton) $50.00
Minimum fee in lieu of tonnage fees (300 pounds or less):
Solid waste from Iowa City premises subject to a Property $7.00
Tax and City owned property
All other solid waste $7.50
Ordinance No.
Page 4
Section II. Repealer. All ordinances and parts of ordinances in conflict with the provisions of this Ordinance
are hereby repealed.
Section III. Severability. If any section, provision or part of the Ordinance shall be adjudged to be invalid or
unconstitutional, such adjudication shall not affect the validity of the Ordinance as a whole or any section,
provision or part thereof not adjudged invalid or unconstitutional.
Section IV. Effective Date. This Ordinance shall be in effect on July 1, 2022.
Passed and approved this day of , 20
Mayor
Attest:
City Clerk
Approved by
City Attorneys Office
c)
r...,
yam. J�-
0
City of Iowa City
Refuse Collection Rate
Ordinance
First Consideration
April 19, 2022
Nicole Davies,
Finance Director
Refuse Collection Fund:
Yard Waste Collection Fee Rate Increase
Approved as part of FY2023 budget and three-year financial plan
Rate increase of $1.50 per dwelling unit per month, mirrored increase Il
for additional carts
Monthly rate goes from $2.00 to $3.50 per month on July 1
Will generate approximately $285,000 annually to cover increased set-
out rates and cost of fuel, equipment and labor.
The Yard Waste collection fee has not been increased since first
adopted in FY2018.
Yard Waste Collections Operations Growth
4,000
3,500
3,000
2,500
2,000
1,500
1,000
500
0
Curbside Yard Waste Operations
2017 2018 2019 2020 2021
$360,000
$350,000
$340,000
$330,000
$320,000
$310,000
$300,000
$290,000
$280,000
$270,000
$260,000
Refuse Collection Fund:
Curbside Solid Waste Rate Increase
Approved as part of FY2023 budget and three-year financial plan
Rate increase of $1.00 per dwelling unit per month, mirrored increase
for additional carts
Monthly rate goes from $12.00 to $13.00 per month on July 1
Will generate approximately $190,000 annually to cover increased
tonnages and cost of fuel, equipment and labor.
Last curbside solid waste fee increase was $0.20 per dwelling unit per
month in FY2018
1
Solid Waste Collections Operations Growth
10,400
10,200
10,000
9,800
9,600
9,400
9,200
Curbside Solid Waste Operations
2017 2018 2019 2020 2021
$1,600,000
$1,550,000
$1,500,000
$1,450,000
$1,400,000
$1,350,000
$1,300,000
$1,250,000
$1,200,000
Refuse Collection Fund:
Curbside Recycling Fee Rate Increase
Approved as part of FY2023 budget and three-year financial plan
Rate increase of $.50 per dwelling unit per month
Monthly rate goes from $6.00 to $6.50 per month on July 1
Will generate approximately $95,000 annually to cover increased
tonnages and cost of fuel, equipment and labor.
Last curbside recycling fee increase was $0.90 per dwelling unit per
month in FY2021
Curbside Recycling Operations Growth
3,000
2,500
2,000
1,500
1,000
500
0
Curbside Recycling Operations
j
2017 2018 2019 2020 2021
$1,200,000
$1,000,000
$800,000
$600,000
$400,000
$200,000
$-
Refuse Collection Fund Financial
Projections
Projected Revenues vs. Expenditures
Slides: changed...
Fund:Refuse Collection Fund
$5
$4.75
2 $4.5
0
E
$4.25
$4
$3.75
2022 Revised 2023 Budget 2024 Projected 2025 Projected 2026 Projected 2027 Projected
Budget
Tota I Expenses -A- Total Revenue
Refuse Collection Fund
Rate Changes
Approved as part of FY2023 budget and three-year financial plan
Curbside Yard Waste rate increase of $1.50 per dwelling unit per month, mirror
iiiiimr
the additional cart fee
Curbside Solid Waste rate increase of $1.00 per dwelling unit per month, mi rored i
the additional cart fee
Curbside Recycling rate increase of $.50 per dwelling unit per month
Total estimated $570,000 annual increase in revenues for the Refuse Fund